## 2026-06-05 — hermes — AM look-ahead (cron)

> NOTE: Ongoing Jobs/ folder is a skeleton — data pulled from Upcoming/ for this run.

### Programme status
- **Week 6** (1–6 Jun): EA Zone 3 — 4 pours × 160 m² + 122 m² = **722 m²**. EA complete target Sat 6 Jun.
- **Today (Fri 5 Jun):** Likely pour day 4 of Zone 3.
- **Float ledger:** Baseline 3.0 wks (no adjustments logged yet — Week 6 entry missing).

### ⚠️ Blockers / overdue items
- **Sub-base S/SE handover: MISSING.** Deadline was 15 May. Zone 1–3 forming cannot start without certified sub-base.
- **Claim 1 (25 May) — OVERDUE.** $25–35K target. No claim submitted. Rev 0 LD risk accruing.
- **Cat A RFIs — ALL 10 still pending written response.** These are mobilisation blockers, sent 29 Apr.
- **Job Tracker empty** — no hours, no materials, no productivity logged. Claims will be indefensible.
- **Daily diary missing** for 30 Apr through 4 Jun.

### RFIs to chase (Cat A — top priority)
All 10 Cat A: RFI-A1 through RFI-A10. Specifically:
- **A1** Sub-base certification (handed over / not)
- **A2** Survey + setting out responsibility + levels
- **A3** Concrete pump — who books, what type, available?
- **A4** Batching plant nomination + order lead time
- **A5** Mix designs (MPa, agg size, colour, slump) for each pavement type
- **A6** Connolly joints delivery + secure storage
- **A7** Exclusion zones + traffic control operational?
- **A8** HammerTech induction slot — crew can't foot on site without this
- **A9** Steel reinforcement delivery + laydown area
- **A10** Blinding layer confirmation in S/SE zone

### Subbies
No subcontractors booked. Subbie schedule empty.

### Deliveries expected today
None recorded. Check with Rocky on-site.

### Actions needed from Rocky
1. Confirm whether any Cat A RFI responses have come in by email (Alvey hasn't updated the register)
2. Chase Joel Alvey for all 10 Cat A responses — email or call today
3. Confirm HammerTech induction slot ASAP — crew can't be on site without it
4. Submit Claim 1 immediately — already 11 days overdue
5. Begin filling Job-Tracker.md with hours from past weeks (30 Apr – 4 Jun)
6. Confirm sub-base status — if still not handed over, raise formal delay notice