# 2631 Hornsby — Site Diary: 10 July 2026 (Friday)

## Crew
- **Rocky** (boss/supervisor) — 5pm finish
- **Hus** — with Liam on Connelly joints + infills
- **Donal** — with Rocky on shutter alignment
- **Liam** — supervising the carpenters, with Hus on Connelly joints + infills
- **Steele** — footpath after break
- **4 steel fixers** on footpath — tidied steel + ~60m of other side
- **1 labourer** — with Rocky's crew
- *(Surnames TBC for several)*
- *(Earlier morning note of "16 fixers + 3 capitors" was wrong — corrected to 4 fixers + 1 labourer. Capitor = carpenter.)*

## Weather
Overcast, hazy at times, late sun breaks. Fine for works — no rain.

## Work Completed
**VAR-005: ON HOLD — NO WORK on VAR-005 today.** Day was **footpaths only**.

- **Rocky + Donal:** 65m of shutter aligned and set to height.
- **Hus + Liam:** Connelly joints set; other side infilled and formed. Console joints fixed.
- **4 steel fixers:** tidied up steel for the completed footpath + ~60m done on the other side.
- **Steele:** on footpath after break.
- **Hus:** also stripping plastic off the blocks (morning).

## Photos
16 photos filed in vault.

## Key Outputs
- 65m shutter aligned and set to height
- Connelly joints set
- ~60m of other side fixed
- Footpath steel tidied

## Delays / Disruptions
- Seed fixer team running late (7:34am — noted)
- VAR-005 stood down for the day

## Client Instructions
- VAR-005 on hold

## Safety / TBT
- Not reported

## Sign-off
Draft — pending Rocky approval.