# Note on Head Contract folder

For job 01-2275 (HPE Field of Play Hornsby):

The engagement document is a **Subcontract Order** (PO) issued by Solutions Plus Built Pty Ltd. This is filed under `01b - Purchase Orders/` because Solutions Plus's PO format doubles as the subcontract — they call it a "Subcontract Order".

There is **no separate Head Contract / MSA** between LFCS and Solutions Plus for this job — the PO IS the contract.

All contractual clauses are in:
- `01 - Contracts and POs/01b - Purchase Orders/PO-S01-2275-011-Signed.pdf`

Key clauses worth knowing:
- **Section 8 VARIATIONS** — Clause 8.1: 2 Business Days to respond to a Direction
- **Section 9 DELAYS / EOT** — Clause 9.4.2: 2 Business Days to give Notice of Delay
- **Clause 9.4.4** — Failure to give notice within time = **LOSS of EOT rights** (legal teeth on the 2-day rule)
- **Clause 9.4.3** — EOT Claim within 5 Business Days of delay cessation