# 24-Week Programme — 01-2275 HPE Field of Play Hornsby

- **Commencement:** 30 April 2026
- **Completion:** 15 October 2026
- **Working hours:** 7:00am – 5:30pm
- **Working days:** 6 days/week (Mon-Sat)
- **LD:** $250/day
- **Float:** ~3 weeks (more than contract requires)
- **Productivity baseline:** 160 m²/day | Stretch: 180+ m²/day

| Wk | Dates | Activities | Pour area | Cum. m² | Claim |
|---|---|---|---|---|---|
| 1 | 30 Apr – 2 May | **START.** 3-day week (Thu–Sat). Mobilise. HammerTech inductions. Site set-up + laydown. Confirm survey S/SE. Begin stair forming Day 1. | – | – | – |
| 2 | 4 – 9 May | Stair forming complete. Stair reo (Days 1–3). Pre-pour inspection. Stair pour end of week. Form pram ramp 1. | Stairs | – | – |
| 3 | 11 – 16 May | Pram ramp 1 reo + pour. Pram ramp 2 form + reo + pour. Begin EA forming first S/SE panels. | Ramps | – | – |
| 4 | 18 – 23 May | EA Zone 1: 5 pours × 160 m² = **800 m² exposed aggregate**. Wash + cure each panel D+1. | 800 | 800 | – |
| 5 | 25 – 30 May | EA Zone 2: 5 pours × 160 m² = **800 m²**. ► **CLAIM 1 due 25 May** (stairs + ramps + 800 m² EA) | 800 | 1,600 | **CLAIM 1** |
| 6 | 1 – 6 Jun | EA Zone 3: 4 pours × 160 m² + balance 122 m². **EA COMPLETE.** | 722 | 2,322 | – |
| 7 | 8 – 13 Jun | Transition to Broom Finish. Begin BF Zone 1 forming. 4 BF pours = 640 m². | 640 | 2,962 | – |
| 8 | 15 – 20 Jun | BF Zone 2: 5 pours × 160 m² = **800 m²**. ► **CLAIM 2 due 25 Jun** (all EA + BF progress) | 800 | 3,762 | **CLAIM 2** |
| 9 | 22 – 27 Jun | BF Zone 3: 5 pours × 160 m² = **800 m²**. | 800 | 4,562 | – |
| 10 | 29 Jun – 4 Jul | BF Zone 4: 5 pours × 160 m² = **800 m²**. | 800 | 5,362 | – |
| 11 | 6 – 11 Jul | BF Zone 5: 5 pours × 160 m² = **800 m²**. ► **CLAIM 3 due 25 Jul** | 800 | 6,162 | **CLAIM 3** |
| 12 | 13 – 18 Jul | BF Zone 6 balance: 207 m². **BF COMPLETE.** Key joints begin — install 400 m. | 207 | 6,369 | – |
| 13 | 20 – 25 Jul | Key joint installation: 400 m. Concurrent defect inspection and rectification. | – | – | – |
| 14 | 27 Jul – 1 Aug | Key joint balance: 484 m. **KEY JOINTS COMPLETE (1,284 m).** ► **CLAIM 4 due 25 Aug** | – | – | – |
| 15 | 3 – 8 Aug | QA walk-through. Engineer sign-off. Solutions Plus defect list issued. | – | – | **CLAIM 4** |
| 16 | 10 – 15 Aug | Defect rectification. Cure sealer application (if VO-003 approved). | – | – | – |
| 17 | 17 – 22 Aug | Make-good. Final surface inspections. Begin Annexure B closeout docs. ► **CLAIM 5 due 25 Sep** | – | – | – |
| 18 | 24 – 29 Aug | As-built drawings preparation. O&M manuals. Product warranties. | – | – | – |
| 19 | 31 Aug – 5 Sep | Statutory declaration preparation. Deed of Release. Final RFIs resolved. | – | – | **CLAIM 5** |
| 20 | 7 – 12 Sep | Closeout documentation final review. Site demob planning. | – | – | – |
| 21 | 14 – 19 Sep | Defects liability check. Outstanding items resolved. Target Practical Completion sign-off. | – | – | – |
| 22-24 | 21 Sep – 15 Oct | **FLOAT / CONTINGENCY** — 3 full weeks buffer for weather delays, access issues, rectifications. **TARGET: COMPLETE BY WK 21.** FINAL CLAIM submitted 25 Oct. | – | 6,369 | **FINAL CLAIM** |

## Daily pour cycle (concrete pavement)

| Day | Activity | Detail | Crew |
|---|---|---|---|
| N–2 & N–1 | Form next panel | Edge forms, star pickets, thickened edges, expansion joints | 2 men |
| N–1 | Reinforce | SL72 mesh (or N12 bar as spec'd), chairs, tie wire | 2 men |
| **N (POUR)** | Pre-pour check | Formwork, reo cover, levels, services clear. **Solutions Plus sign-off.** | All crew + SPB rep |
| **N (POUR)** | Concrete placement | Direct pump, screed, compact edges and thickened zones | 4–5 men |
| N (4–8 hrs after pour) | Broom finish OR float | Broom texture / power float / stop for retarder (EA) | 2–3 men |
| N (same day, EA only) | Apply surface retarder | Dulux Avista Retarder. Shade from sun/wind. Monitor set. | 1 man |
| N+1 AM (all types) | Apply Fosroc Concure AV | Evaporation retarder fine mist | 1 man |
| N+1 AM (EA only) | High-pressure wash | 2,000 psi minimum. Start low, work uphill. | 2 men |
| N+1 (after dry) | Apply Fosroc Concure A99 | Roller at 5 m²/L. Trafficable in 24 hrs. | 1 man |
| N+5 (optional) | Apply Dulux Avista Sealer | Day 5+ after full cure. Enhance + protect. | 1 man |

## Programme float ledger

OpsMan tracks float weekly. Trigger an alert if float drops below **3 weeks** (= original contract margin) and an EOT/variation case must be opened.

| Week ending | Float remaining | Cause of any change | Action |
|---|---|---|---|
| 2 May 2026 (Wk 1) | 3.0 wks | Baseline | – |