# Daily Diary — 2026-04-30

**Status:** mobilisation delayed. Rocky in office. No crew on site.

## Weather
TBC

## Crew on site
None — mobilisation held.

## Work completed
Nil — delay. No site access / mobilisation.

## Materials in
Nil.

## Issues / RFIs / variations raised
- Mobilisation delayed. Cause TBC — check with Solutions Plus (client). Log variation/EOT trigger flag.

## Photos
None.

## Docket
N/A.

## Notes
- Programme shows Day 1 start 30 April. No crew on site.
- Rocky flagging delay from office. Need to confirm reason (client instruction, access, weather, etc.) and whether this triggers an EOT.