job_no: TBC
project_code: TBC
job_name: Ford Civil - Parramatta
hc: Ford Civil Pty Ltd
end_client: TBC (Parramatta CBD precinct — likely PHIVE/Square 4 area paver + L4 link bridge)
site: Parramatta, NSW
postcode: 2150
scope: formwork-carpentry (paver install, edgeboard, L4 link bridge formwork)
design_maturity: TBC — signed subcontract (LF Standard Subcontract Rev 1.4) so design at construction-issue
outcome: in-progress (winding down — Apr 2026 revenue dropped 87% from peak)
status: Ongoing
source: "[source: friend-vault] C:/Users/mclou/lfcs-precedent-staging/lfcs-obsidian-vault-mirror/01 - Jobs/Ford Civil - Parramatta/_Job Overview.md"
ingested: 2026-05-10 by lfcs-orchestrator (lfo-precedent-import)
purpose: Precedent reference for `lfo-precedent-finder` — formwork-carpentry, link-bridge + paver scope, Parramatta CBD precinct
---

# Ford Civil - Parramatta

**Folder structure note:** Source is Hus's vault `01 - Jobs/` single-file shape. Has actual SIGNED subcontract referenced (`LF Construction Services - Standard Subcontract Agreement(Short Form).Rev1.4.pdf`) plus 5 sub-statements (942/945/947/951/954). `digest-only` mode — artefacts not mirrored.

## Quick metadata

| Field | Value |
|---|---|
| HC | Ford Civil Pty Ltd (peak month: Jan 2026 = $164,838 from Parramatta — single largest LFCS revenue month in dataset) |
| End-client | TBC — Parramatta CBD area (PHIVE/Civic Square / Council infrastructure plausible based on "L4 link bridge + paver install") |
| Site | Parramatta, NSW |
| Postcode | 2150 |
| Project code | TBC |
| Scope | Formwork & carpentry — paver install, edgeboard, L4 link-bridge formwork |
| Drawings | TBC (referenced in friend-vault; not in source single-file overview) |
| BoQ | TBC — engagement is mixed day-labour + sub-statement; likely lump-sum elements present |
| Rate Build-up | Hus's `08 - Rates/Rate Cards` + `08 - Rates/FRP Rates Development` |
| Pre-Pricing-Grill | TBC |
| Letter of Offer | LF Standard Subcontract Rev 1.4 (signed — friend-vault path) |
| Tender Summary | TBC |
| Inclusions / Exclusions | TBC |
| Drawing Index | TBC |
| Final submitted total ex GST | TBC — sub statements 942/945/947/951/954 represent progress claims; cumulative not summarised in source |
| Outcome | Ongoing — winding down (Apr 2026 = $20,265 vs Mar 2026 = $161K-class) |

## For `lfo-precedent-finder`

Strong-match signals:
- HC = Ford Civil Pty Ltd
- Site type = CBD precinct civils with elevated link-bridge + paver/edgeboard scope (formwork-carpentry, mid-complexity)
- Scope items = formwork + carpentry (no concrete-place / steel-fix flagged in source)
- Design maturity = signed subcontract (construction-issue / IFC equivalent)
- Site postcode region = 2150 (Parramatta — west Sydney metro, ~25 km W of CBD)

Weak-match signals (extract on deep-pass if precedent fires):
- Final submitted total ex GST — TBC; would require pulling all 5 sub-statements + variation register
- Specific complexity factors — L4 link bridge = working-at-height + crane staging precedent value
- LAFHA decision — likely OUT (Parramatta from Botany ~30 min via M5/M4 — under §13.1 threshold)
- Adverse weather posture — variation/day-labour basis (no exposure to Inclement Weather risk)
- Site exposure category — non-coastal urban CBD

## Open follow-ups

1. Pull subcontract Rev 1.4 PDF — extract scope schedule + rate matrix for FRP precedent value.
2. Sum sub-statements 942/945/947/951/954 → total contract value to date.
3. Identify end-client (Parramatta Council? Walker Corp? other developer?).
4. Capture L4 link bridge methodology (crane assumptions, propping, formwork system used) — high-value precedent for future bridge/elevated bids.
5. Variations log: source notes "None raised" — confirm vs sub-statement contents (variations may be embedded).