job_no: TBC
project_code: MLP-30-Glen-St-Carpentry (subcontract no.)
job_name: MLP - 30 Glen St
hc: MLP
end_client: TBC (Milsons Point high-rise developer)
site: 30 Glen St, Milsons Point NSW
postcode: 2061
scope: carpentry-joinery-fitout (doors, skirting, timber capping, kitchen exhaust riser, Level 26/27)
design_maturity: IFC (subcontract signed = construction)
outcome: in-progress (signed contract 09/10/2025; PC01 paid; PC02 overdue)
status: Ongoing
source: "[source: friend-vault] C:/Users/mclou/lfcs-precedent-staging/lfcs-obsidian-vault-mirror/01 - Jobs/MLP - 30 Glen St/_Job Overview.md"
ingested: 2026-05-10 by lfcs-orchestrator (lfo-precedent-import)
purpose: Precedent reference for `lfo-precedent-finder` — MLP carpentry-joinery commercial fitout, lump-sum + variations
---

# MLP - 30 Glen St

**Folder structure note:** Hus's vault has BOQ + Quote (Revised) + Progress Claim + Exhaust Riser BOQ + Job Tracker as `.xlsx` files in Windows folder `Jobs/Ongoing Jobs/MLP - 30 Glen ST/` — not mirrored here per friend-vault read-only constraint. Source paths only.

## Quick metadata

| Field | Value |
|---|---|
| HC | MLP |
| End-client | TBC (Milsons Point Level 26/27 commercial fitout) |
| Site | 30 Glen St, Milsons Point NSW |
| Postcode | 2061 (LAFHA OUT per §13.1: ~12 min from Botany) |
| Project code | MLP-30-Glen-St-Carpentry (subcontract reference) |
| Scope | Carpentry & joinery: doors, skirting, timber capping, kitchen exhaust riser, timber capping over hob, L26/27 |
| Drawings | TBC |
| BoQ | `BOQ - 30 Glen St, Milsons Point.xlsx` + `Exhaust Riser - BOQ.xlsx` (in Hus's vault) |
| Rate Build-up | TBC |
| Pre-Pricing-Grill | Not applicable (carpentry-fitout, not the 4-item LFCS scope) |
| Letter of Offer | `Quote - 30 Glen St, Milsons Point (Revised).pdf` |
| Tender Summary | Quote (Revised) PDF |
| Inclusions / Exclusions | TBC — not extracted in `_Job Overview.md` |
| Drawing Index | TBC |
| Final submitted total ex GST | TBC; PC01 = $25,980.78 inc-GST = ~$23,619 ex; PC02 var = $15,063.40 inc-GST = ~$13,694 ex |
| Outcome | Won 09/10/2025 (countersigned subcontract); in-progress — PC02 OVERDUE (red flag) |

## For `lfo-precedent-finder`

Strong-match signals:
- HC = MLP (most-used MLP precedent — has signed subcontract + claim history)
- Site type = commercial-fitout high-rise (Level 26/27 — vertical access constraint)
- Scope items = carpentry+joinery (out of 4-standard LFCS set)
- Design maturity = IFC (signed contract)
- Site postcode region = 2061 Milsons Point (LAFHA OUT per §13.1)

Weak-match signals:
- Variation discipline: 2 pending VARs (kitchen exhaust riser GPA9.1-251023, timber capping over hob) → MLP allows variation pathway
- Retention: $8,690 held on PC01 — confirm % (likely 5% or 10%)
- Payment behaviour: PC02 OVERDUE 30/04/2026 — **MLP cashflow risk flag for future bids**

## Open follow-ups

1. End-client / building name not in `_Job Overview.md`
2. Total subcontract value not extracted (need BOQ.xlsx read)
3. Variation valuations TBC
4. Lessons-learned candidate: **MLP overdue claim → flag MLP credit risk on next MLP bid; potentially require shorter payment terms or payment guarantee.** Queue to `proposals-pending.md`.