job_number: 2602
client: Dec Projects (Robert)
client_email: tenders@decprojects.com.au
end_client: TBC (Old Munmorah Power Station decommissioning, NSW)
designer: Northrop Consulting Engineers
site: Station Road, Colongra NSW (Munmorah Bridge over Hammond Canal)
status: upcoming
type: price                              # subcontract F+R+P package, lump-sum tender
contract_price: TBC                      # filled after pricing
hourly_rates_inherit: lfcs-standards/rate-card.md
client_signatory:
  name: Robert (surname TBC)
  role: QS / Head Contractor
  phone: TBC
  email: tenders@decprojects.com.au
start_date: TBC                          # confirm Tuesday call
target_pc: TBC                           # confirm Tuesday call
bid_due: 2026-05-07 (Wed)
qs_call: 2026-05-05 (Tue evening)
created: 2026-05-03
created_by: cowork-hq (one-time exception scaffold; ongoing work owned by cowork-lfcs)
---

# Job Brief — 2602 Dec Projects — Munmorah Bridge

## Scope (1–3 sentences)

Subcontract F+R+P (Formwork, Reinforcement, Pour) package for the new **Munmorah Bridge over Hammond Canal** at Station Road, Colongra (old Munmorah Power Station site). 34m overall length, 32.4m span between bearings, 8.2m carriageway, 4 × Type T4 Super-T girders on 900 dia bored piles into Unit 4 rock. AS5100 (2017) bridge code. **LFCS prices substructure (abutments, wingwalls), superstructure (deck), approach slabs, and barrier installation labour. Pile installation, girder/bearing/parapet supply, and Super-T cranage are NOT in LFCS scope.**

## Quantities at a glance (LFCS scope only)

| Element | Concrete (m³) | Reo (T) | Formwork (m²) | Strip (m²) |
|---|---|---|---|---|
| Abutments | 53.06 | 15.92 | 68.24 | 53.06 |
| Wingwalls | 44.44 | 13.33 | 214.49 | 44.44 |
| Bridge deck | 101.62 | 34.00 | 80.74 | 25.00 |
| Approach slabs | 41.49 | 5.92 | 44.12 | 20.00 |
| **TOTAL** | **~240.6** | **~69.2** | **~407.6** | **~142.5** |

Plus: bearings install (1 item), drainage 64.8m, expansion joints 59.4m, scaffolding/walkways (1 item), Super-T launch labour (cranage excl), parapet lift (cranage incl), saw-cut canal wall section (1 item).

## Key risks identified at quote stage

1. **Drawings are NOT FOR CONSTRUCTION.** Stamped "Issue for Information" — preliminary sketch. Northrop notes scaled CAD will be produced post-award. Scope creep risk on drawing rev. → Mitigation: lock pre-agreed VO rates + assumption clause in submission.
2. **5+ month gap** between drawing/BOQ issue (Aug-Dec 2025) and tender close (May 2026). Material costs may have moved. → Mitigation: rate validity clause (e.g. "rates valid 30 days from submission, subject to review on award").
3. **Existing services in work zone**: live electrical to control room, water main against canal wall, 1200DN dirty water line, monitor well, electrical pits. Strike-and-stop risk. → Mitigation: exclude service strike costs unless head contractor warrants location data.
4. **Existing channel wall condition**. Saw-cut + Renderoc ST06 patch repair on exposed reo. → Mitigation: exclude pre-existing defects beyond nominated patch repair.
5. **Pile coordination**. Pile work not in LFCS scope but abutment/wingwall starts depend on top-of-pile being on time + on level. → Mitigation: programme dependency clause in submission.
6. **Super-T cranage**. Excluded from BOQ. Either Dec Projects has separate cranage subbie, or LFCS prices it separately. Crane size driven by girder weight/length. → Mitigation: confirm Tuesday; if LFCS to provide, get cranage quote before pricing.
7. **Concrete + reo specs not in BOQ**. Bridge concrete typically 50MPa+, reo grade not stated. → Mitigation: confirm Tuesday before final pricing.
8. **Power station site access**. Old Munmorah PS — likely security-cleared, induction required. Unknown working hours, vehicle access. → Mitigation: confirm Tuesday + price induction time/risk.
9. **Hammond Canal water flow**. Saltwater? Tidal? Cofferdam needed for abutment work? → Mitigation: confirm with site visit + price accordingly.
10. **Reo intensity 287 kg/m³ overall**. Heavy. Bar fixing labour rate must reflect this density.

## Subbies / labour expected

- Concrete supply: TBC (local Newcastle/Central Coast supplier — Boral, Holcim, Hanson)
- Reo supply + bend/cut: TBC (Onesteel, Infrabuild, or local)
- Formwork system: TBC (formhire vs build-to-suit)
- Cranage (if in scope): TBC
- Concrete pump: TBC
- Internal LFCS labour: TBC — confirm size of crew per pour

## Key dates / milestones

- 2026-05-03 (Sun) — files received, bid prep started
- 2026-05-04 (Mon) — Rocky at office; finalise question list, start pricing skeleton
- 2026-05-05 (Tue evening) — QS call with Dec Projects (Robert)
- 2026-05-06 (Wed) — finalise rates, inclusions/exclusions, submission cover
- 2026-05-07 (Wed) — **bid due** (close date TBC — confirm format + closing time Tuesday)

## Notes from planning session

Cowork-hq one-time scaffold pass on 2026-05-03 evening. Files extracted from PDF/xlsx text:
- Structural drawings (`2602_STR_Munmorah-Bridge-TCE_Rev1_2025-08-29.pdf`) — 3 pages A1, dated 29.08.25, drafted by R Officer @ Northrop Newcastle.
- Civil drawings (`CI251342_Munmorah Power Station SW_REV 2 working.PDF`) — 4 pages A1, dated 17.09.25, drafted by P Cornish @ Northrop Sydney. NOT in LFCS scope (reference only — pavement/stormwater/services).
- BOQ (`P424-HCB-BOQ-FRP-Package.xlsx`) — Rev A, dated 11.12.25. 57 rows, all rates blank (LFCS to fill).

**Rocky to drop original files** into the right folders tomorrow at the office:
- Both PDFs → `03 - Plans and Specifications/03a - Issued for Construction/`
- BOQ xlsx → `02 - Scope and Pricing/02b - BOQ and Rate Schedules/`
- Pricing working copy of BOQ → `02 - Scope and Pricing/02a - Quotes and Estimates/`

See `00-Bid-Prep.md` for full analysis. See `06 - Correspondence/06c - Meeting Minutes/Pre-Call-Questions-2026-05-05.md` for the Tuesday QS call agenda.

## Open from this scaffold

- [ ] Rocky: drop original 3 files into vault folders tomorrow
- [ ] Rocky: vision-pass each drawing yourself before Tuesday (text extract is NOT a substitute for reading drawn detail, dimensions, geometry)
- [ ] Rocky: open Tuesday call notes doc, fill in answers as the call happens
- [ ] cowork-lfcs: fill out `Inclusions-Exclusions.md` post-call
- [ ] cowork-lfcs: build pricing working sheet from the BOQ
- [ ] cowork-lfcs: draft submission cover + qualifications page