---
job_no: 2627
job_name: Airey Park — Homebush West
phase: phase-3-worker-first-pass
authored_by: lfcs-pricing
session_id: 80b1f893-d887-4130-b96f-dd48d5450edd
date: 2026-05-08
basis: STR25020 rev D + P171342-SP-001-0 rev 0; intake-locked envelope 2026-05-08T08:33:58Z
labour_rate_per_hr_aud: 95.00
labour_loaded_multiplier: 1.3225  # 1.15 cont × 1.15 margin (sequence: cont→margin)
materials_loaded_multiplier: 1.3225  # 1.15 margin × 1.15 cont (sequence: margin→cont; Rocky-review flagged)
posture: defensible-for-variations
quantity_basis: PROVISIONAL — architectural setout RFI gates final quantities (±20-30% confidence band)
status: WORKER-DRAFT — Phase 4 sanity-check pending Rocky+Liam review
NOT_FOR_EXTERNAL_DISTRIBUTION: true
sanitisation: NOT_REQUIRED (internal artefact; external submission derives via L1+L2 sanitisation)
---

# 2627 — First-Pass Priced Take-Off

## Pricing basis (locked)

| Parameter | Value | Source |
|---|---|---|
| Labour rate | $95/hr blended | standing-context §1.3; build-up 8h×$85 + 2h×$105 + 1h×$120 ÷ 10h |
| Labour loading | direct × 1.15 cont × 1.15 margin = **1.3225** | envelope override (Rocky 2026-05-08 pre-IFC posture) |
| Materials loading | direct × 1.15 margin × 1.15 cont = **1.3225** | envelope override (orchestrator parallel uplift; Rocky-review-flagged) |
| Concrete grade | 32 MPa structural (footings + slab on ground + DEB1); 35 MPa pavement-flexural for 125mm pathway *(RFI)* | STR25020 S100/S200 + pavement spec Table 1 |
| Site exposure | inland | standing-context §1.2 + drawings A1 cover schedule |
| LAFHA | OUT | Sydney crew, Sydney metro site (~25 min Botany→Homebush West) |
| Adverse weather | exclude as variation at day-labour rates | std exclusion 7 |
| Working hours | Mon–Fri 7:00–15:30 (Saturday TBD) | RFQ silent; default + RFI |
| Cure period | 7 days | pavement spec §10.1.1 (corrected from skeleton A7 14-day) |

## Productivity adjustments built into per-line rates

| Element | Factor | Rationale |
|---|---|---|
| DEB1 deep-edge-beam | +30% labour-hours | 1200 deep × 300 thick × 13 lin m; multi-layer cage; tremie place; heavy props; slow strip |
| Existing-slab interface (tooth slab + tooth stair + drill+epoxy dowels + wall-removal coordination) | +15-20% labour-hours | drawings S201 sections 1+2 + S200 typ toothing detail |
| Stepped SF1 seating terrace (3 lifts) | +10-15% labour-hours | drawings S51 stepped strip footing |

## Per-line take-off

### Formwork (S+I+strip)

| # | Line item | Qty | Unit | Form face m² | Productivity (MH/m²) | MH | Lab direct | Mat direct | Lab loaded (×1.3225) | Mat loaded (×1.3225) |
|---|---|---|---|---|---|---|---|---|---|---|
| F1 | SF1 perimeter strip footing forms (gridline 1-2 + side returns A+F) | 30 | lin m | 30 | 0.30 | 9.0 | $855 | $750 | $1,131 | $992 |
| F2 | SF2 internal strip footing forms (gridline 2 C-E) | 10 | lin m | 10 | 0.30 | 3.0 | $285 | $250 | $377 | $331 |
| F3 | SF1 stepped lift forms (terrace 3 lifts) | 18 | lin m | 25 | 0.345 (+15% step) | 8.6 | $820 | $625 | $1,084 | $827 |
| F4 | DEB1 drop edge beam (1200 deep × 300 thick) | 13 | lin m | 22 | 0.39 (+30% deep) | 8.6 | $815 | $1,050 *(incl. heavy props)* | $1,078 | $1,389 |
| F5 | 150mm internal slab edge | 30 | lin m | 5 | 0.30 | 1.5 | $143 | $125 | $189 | $165 |
| F6 | 125mm pathway slab edge | 80 | lin m | 10 | 0.30 | 3.0 | $285 | $250 | $377 | $331 |
| F7 | Seating terrace 150 slab + step + nosing forms | 25 | m² | 25 | 0.345 (+15% complex) | 8.6 | $820 | $625 | $1,084 | $827 |
| F8 | Riser bespoke form (S200 wall-removal infill) | 1 | item | small | bespoke | 3.0 | $285 | $50 | $377 | $66 |
| **Formwork subtotal** |  |  |  | **127** |  | **45.3** | **$4,308** | **$3,725** | **$5,697** | **$4,927** |

### Steel fix (LFCS supplies plastic spacers; HC supplies bars + mesh + tie wire + cast-ins)

| # | Line item | Qty | Unit | Productivity | MH | Lab direct | Mat direct | Lab loaded | Mat loaded |
|---|---|---|---|---|---|---|---|---|---|
| SF1 | SL82 mesh top + bottom — 150mm internal slab | 338 | m² fixed | 30 m²/MH | 11.3 | $1,069 | $169 *(plastic spacers)* | $1,414 | $223 |
| SF2 | SL82 mesh top — 125mm pathway slab | 120 | m² fixed | 30 m²/MH | 4.0 | $380 | $60 | $503 | $79 |
| SF3 | 4-F12 TM T+B + R10-600 ties — SF1 strip footings | 150 | kg | 50 kg/MH | 3.0 | $285 | $50 | $377 | $66 |
| SF4 | 3-F12 TM T+B + R10-600 ties — SF2 strip footings | 25 | kg | 50 kg/MH | 0.5 | $48 | $10 | $63 | $13 |
| SF5 | 4F12 TM + N12-200 horiz + N12-300 horiz — DEB1 cage | 90 | kg | 38.5 kg/MH (+30% deep) | 2.3 | $222 | $30 | $293 | $40 |
| SF6 | N16-400 vert starter bars SF1 (lap 600 to wall above) | 40 | kg | 50 kg/MH | 0.8 | $76 | $15 | $101 | $20 |
| SF7 | 2N16-200 Z-bars 800 cog — seating terrace walls | 30 | kg | 50 kg/MH | 0.6 | $57 | $10 | $75 | $13 |
| SF8 | N12-200 horiz each face — seating terrace walls | 40 | kg | 50 kg/MH | 0.8 | $76 | $15 | $101 | $20 |
| SF9 | N12-300 U-bars + N12-300 horiz — Section 3 minor footing | 10 | kg | 50 kg/MH | 0.2 | $19 | $5 | $25 | $7 |
| SF10 | N12-200 T+B — stair tooth (existing-slab interface +15%) | 15 | kg | 43.5 kg/MH | 0.34 | $33 | $5 | $44 | $7 |
| SF11 | 2N12-1200 long trimmer bars at slab openings (~6 openings) | 14.4 | m | ~50 kg total | 0.2 | $19 | $5 | $25 | $7 |
| SF12 | Drill + epoxy N12-400 GALV dowel bars 150mm into existing slab | 50 | dowels | 0.05 MH/dowel | 2.5 | $238 | $250 *(epoxy)* | $315 | $331 |
| **Steel fix subtotal** |  |  |  |  | **26.5** | **$2,522** | **$624** | **$3,335** | **$825** |

### Concrete place + finish (HC supplies concrete + pump + truck; LFCS supplies vibrator + finishing tools)

| # | Line item | Qty | Unit | Crew × hrs | MH | Lab direct | Mat direct | Lab loaded | Mat loaded |
|---|---|---|---|---|---|---|---|---|---|
| CP1 | 150mm internal slab pour + finish (broom/trowel/edge) | 25.4 m³ + 169 m² finish | m³+m² | 4 × 12 (incl. existing-slab interface portion +5%) | 47 | $4,465 | $50 | $5,905 | $66 |
| CP2 | 125mm pathway slab pour + finish | 15 m³ + 120 m² finish | m³+m² | 4 × 8 (staged ~3 pours) | 31 | $2,945 | $30 | $3,895 | $40 |
| CP3 | DEB1 drop edge beam pump-place + tremie + vibrator (+30% deep penalty) | 4.7 m³ | m³ | 4 × 4 | 16 | $1,520 | $30 | $2,011 | $40 |
| CP4 | SF1 strip footings pour | 6.8 m³ | m³ | 4 × 2.7 | 11 | $1,045 | $20 | $1,382 | $26 |
| CP5 | SF2 strip footings pour | 1.5 m³ | m³ | 4 × 0.6 | 2.4 | $228 | $5 | $301 | $7 |
| CP6 | SF1 stepped seating terrace (+15% stepped penalty) | 5 m³ | m³ | 4 × 3.6 | 14.4 | $1,368 | $20 | $1,809 | $26 |
| CP7 | Seating terrace 150 slab decks pour + finish | 3.8 m³ + 25 m² finish | m³+m² | 2 × 5.5 | 11 | $1,045 | $15 | $1,382 | $20 |
| CP8 | Concrete riser + stair tooth + Section 3 minor (existing-slab interface) | 1.5 m³ | m³ | bespoke | 6 | $570 | $10 | $754 | $13 |
| CP9 | Cylinder + flexural beam preparation + delivery (per pavement spec §14) | 3 sublots | sublot | 0.5 MH/sublot | 1.5 | $143 | $30 *(moulds amortised)* | $189 | $40 |
| **Concrete place+finish subtotal** |  |  |  |  | **140.3** | **$13,329** | **$210** | **$17,628** | **$278** |

### Curing (polythene + hessian per pavement spec §10; 7-day cycle)

| # | Line item | Qty | Unit | MH | Lab direct | Mat direct | Lab loaded | Mat loaded |
|---|---|---|---|---|---|---|---|---|
| CR1 | Initial poly + hessian install (50 m²/MH) | 344 | m² | 7 | $665 | — | $880 | — |
| CR2 | Daily wet down + check + maintenance (~0.5 MH/day × 7 days) | 7 | day | 5 | $475 | — | $628 | — |
| CR3 | Strip + dispose (80 m²/MH) | 344 | m² | 4 | $380 | — | $503 | — |
| CR4 | Hessian + polythene material (with overlap) | 344 | m² | — | — | $1,446 | — | $1,912 |
| **Curing subtotal** |  |  |  | **16.0** | **$1,520** | **$1,446** | **$2,010** | **$1,912** |

### Joints (HC-supplied: pre-formed filler + isolation polythene + sealant + backing rod; LFCS labour + sawing)

| # | Line item | Qty | Unit | Productivity | MH | Lab direct | Mat direct | Lab loaded | Mat loaded |
|---|---|---|---|---|---|---|---|---|---|
| J1 | Sawn control joints (24-hr saw window) | 60 | lin m | 30 lin m/MH | 2.0 | $190 | $50 *(blade wear)* | $251 | $66 |
| J2 | Keyed construction joints (paint bitumen first cast face) | 25 | lin m | 15 lin m/MH | 1.7 | $161 | $25 *(bitumen)* | $213 | $33 |
| J3 | Expansion joints (preformed filler placement; HC supplies filler) | 10 | lin m | 10 lin m/MH | 1.0 | $95 | — | $126 | — |
| J4 | Isolation joints (10mm polythene strip; HC supplies) | 80 | lin m | 20 lin m/MH | 4.0 | $380 | — | $503 | — |
| J5 | Sealant install + backing rod (HC supplies) | 95 | lin m | 10 lin m/MH | 9.5 | $903 | — | $1,194 | — |
| **Joints subtotal** |  |  |  |  | **18.2** | **$1,729** | **$75** | **$2,287** | **$99** |

### Site overhead + supervision

| # | Line item | Qty | Unit | MH | Lab direct | Lab loaded |
|---|---|---|---|---|---|---|
| SO1 | Pre-pour walk + crew brief + form/reo final inspection (4 pour days × 1 hr crew lead) | 4 | inspection | 4 | $380 | $503 |
| SO2 | Pump/truck direction during pours (5 pour days × 1 hr) | 5 | pour day | 5 | $475 | $628 |
| SO3 | Site setup + breakdown + plant moves (5 weeks × 2 hr/week) | 5 | week | 10 | $950 | $1,256 |
| SO4 | Supervision overhead (HC coordination, safety, daily handovers) | ~15% on direct labour | — | 30 | $2,850 | $3,769 |
| **Site overhead subtotal** |  |  |  | **49.0** | **$4,655** | **$6,156** |

## Roll-up

### Direct totals

| Trade | MH | Labour direct | Materials direct | Trade direct |
|---|---|---|---|---|
| Formwork | 45.3 | $4,308 | $3,725 | $8,033 |
| Steel fix | 26.5 | $2,522 | $624 | $3,146 |
| Concrete place+finish | 140.3 | $13,329 | $210 | $13,539 |
| Curing | 16.0 | $1,520 | $1,446 | $2,966 |
| Joints | 18.2 | $1,729 | $75 | $1,804 |
| Site overhead | 49.0 | $4,655 | — | $4,655 |
| **Total direct** | **295.3** | **$28,063** | **$6,080** | **$34,143** |

### Loaded totals (×1.3225)

| Trade | Labour loaded | Materials loaded | Trade loaded |
|---|---|---|---|
| Formwork | $5,697 | $4,927 | $10,624 |
| Steel fix | $3,335 | $825 | $4,160 |
| Concrete place+finish | $17,628 | $278 | $17,906 |
| Curing | $2,010 | $1,912 | $3,922 |
| Joints | $2,287 | $99 | $2,386 |
| Site overhead | $6,156 | — | $6,156 |
| **Total loaded ex GST** | **$37,113** | **$8,041** | **$45,154** |

## Headline numbers

- **Total ex GST direct: $34,143**
- **Total ex GST loaded (×1.3225): $45,154**
- Loaded uplift over direct: $11,011 (32.25% — matches multiplier)
- Total labour MH: ~295 hrs
- Sanity-check vs Bid Prep §7 magnitude estimate ($48,140 loaded): worker take-off comes in **6% below** §7 estimate. Difference within expected refinement band; §7 was conservative magnitude pre-line-itemisation.

## Variance sources (worker estimate vs sanity §7)

| Line | Worker estimate | §7 estimate | Delta | Reason |
|---|---|---|---|---|
| Total labour direct | $28,063 (295 MH) | $30,400 (320 MH) | −8% | Productivity rates refined per line; less padding |
| Total materials direct | $6,080 | $6,000 | +1% | Aligned |
| Total loaded | $45,154 | $48,140 | −6% | Composite of above |

## Quantity confidence + RFI gate

**All quantities provisional ±20-30% pending architectural setout RFI** (RFI #1 in Bid Prep F3 + Q-G4). Lines most sensitive to architectural confirmation:
- 150mm slab area (currently 169 m² provisional)
- 125mm pathway extent (currently 120 m² provisional)
- Seating terrace footprint (currently 25 m² provisional)
- Joint lengths (derive from slab perimeters)
- Trimmer-bar count at openings (currently 6 provisional)

If architectural plan reduces total slab area by 30%, total drops ~$10K loaded. If increases by 30%, total rises ~$10K loaded.

## RFIs gating final submission

1. **Architectural setout drawings** — HIGH (quantity ±30% band)
2. **Concrete grade for 125mm pathway** — LOW $ (HC pays supply premium)
3. **Pavement spec template carry-over (St Ives reference)** — NIL $ (designer confirmation only)
4. **Working hours + Saturday allowance** — LOW (variation rate if Saturday)
5. **Programme dates + continuous run** — MEDIUM (broken programme = variation rate per std excl 7)
6. **Shelter shop drawings (post footings)** — LOW–MEDIUM (additional pad footings if confirmed)
7. **Stormwater drainage drawings** — LOW (slab penetrations + trimmer count)
8. **Piering** — MEDIUM (scope expansion via variation if confirmed)

## Flag items for Rocky at sanity-check

| Tag | Item | Action |
|---|---|---|
| F1 | Concrete grade conflict 32 vs 35 MPa for 125mm pathway | RFI to designer; LFCS labour unaffected |
| F8 | Materials cont uplift to 15% — orchestrator parallel-applied; Rocky-explicit was labour-only | **Rocky to confirm or revert materials to 1.265** (1.15 margin × 1.10 cont). Magnitude impact ~−$400 on materials direct subtotal if reverted. |
| F9 | Cure period reduced from skeleton-A7 14-day to spec §10.1.1 7-day | Confirmed in Q-G6 grill answer; built into rates |
| Q-A3 | DEB1 heavy props — LFCS-supplied default ($500 incremental in F4) | Confirm LFCS-supply or HC-supply for DEB1 props |
| Q-D2 | Saw-cut 24-hr window risk for late-afternoon pours | Standard pricing; Rocky may add explicit off-hours saw-cut variation line |
| Q-E | Productivity reductions: DEB1 +30%, existing-slab +15-20%, stepped SF1 +10-15% | Confirm calibration at sanity-check |
| Q-F4 | Format choice — both lump-sum + BoQ-response | Confirm at sanity-check or RFQ receipt |
| §7 variance | Worker total 6% below §7 magnitude — within refinement band | Confirm acceptable |

## Worker layered exclusions feed-back to revision-2

Following carve-outs derived from this take-off; **add to exclusions-2627.md revision 2**:

- **A7 corrected:** cure period 7 days (not 14)
- **A10 (NEW):** Existing-slab interface productivity reduction 15-20% built into per-line rates; LFCS not responsible for unforeseen interface conditions beyond drawings rev D
- **A11 (NEW):** DEB1 deep-edge-beam productivity reduction 30% built into rate; LFCS not responsible for delays from DEB1 prop-removal cylinder-test timing per S000 concrete note 9
- **A12 (NEW):** Stepped SF1 seating terrace productivity reduction 10-15% built into rate
- **Detailed Excl 53 (NEW):** Quantities provisional ±20-30% subject to receipt of architectural setout drawings; final price subject to confirmed quantities
- **Detailed Excl 54 (NEW):** Density coring 75-100mm Ø within 2 days per pavement spec §14.2.5 — destructive testing + core repair cost via HC, not LFCS
- **Detailed Excl 55 (NEW):** Late-afternoon pour saw-cut window: if 24-hr SJ saw-cut requires off-hours work per pavement spec §11.3.6, variation at LFCS Rate Card V1.7 night/weekend loading (8-hr minimum charge)

## Sign-off

| Phase | Signer | Status | Date |
|---|---|---|---|
| Phase 3 first-pass complete (worker draft) | lfcs-pricing | Drafted | 2026-05-08 |
| Phase 4 sanity-check sign-off | Rocky + Liam | Pending | — |
| Phase 5 sanitisation L1+L2 (pre-submission) | lfcs-sanitise + lfcs-sanitisation-verify | Pending | — |
