job_no: 2630
client: TCE Contracting
end_client: TBC
site: North Beach, Wollongong (NSW)
status: bid-prep-intake-complete
bid_due: TBC
start_date: TBC
type: Seawall (concrete + structural; civil + landscape + hydraulic + electrical disciplines)
designer: TBC (drawings prefix 7295 + 6367)
created: 2026-05-05
intake_completed: 2026-05-08
created_by: cowork-lfcs (folder scaffold), claude-code-opsman (intake + blind-compare pre-flight)
airtable_job_id: rectFkTBR5LwoaFHV
blind_comparison_session_id: e57c7d98-c90d-48ed-b874-23bf35f19be8
---

# 2630 — TCE — North Beach Seawall, Wollongong

## Status
**Folder scaffolded + IFC pack filed into vault 2026-05-08.** Blind-comparison session active vs Hasibul prior pricing. **Pre-Pricing-Grill not yet started.**

## What we know
- Head contractor: TCE Contracting (same supply chain as 2602 Munmorah Bridge + 2629 Erskine Park WWTP)
- Site: North Beach, Wollongong NSW
- Drawings prefix: `7295` (main pack) + `6367` (electrical + stair-variation pack — older / different design source)
- Disciplines covered in IFC pack: Civil, Structural, Electrical, Landscape & Hydraulic, plus a Crane Placement plan and a Variation - Stairs sub-package
- Hasibul has priced 2630 previously — this is the comparator basis for the blind comparison

## Inbound source (immutable)
`C:/Users/mclou/lfcs-inbound-artefacts/2630/Issued for Construction-20260507T223555Z-3-001/Issued for Construction/`
Sibling folders `As-Built Drawings/` + `Shop Drawings/` exist at `lfcs-inbound-artefacts/2630/` but are out of scope for this round.

## What's filed in vault 03a/
| Discipline | File | Source MTime |
|---|---|---|
| (root) | `7295_Structural Combined_Latest- limited pages.pdf` (excerpt; 17.6 MB) | 2026-04-20 |
| Civil/ | `7295_Civil_Combined.pdf` (2.3 MB) | 2026-03-24 |
| Electrical/ | `6367-E02 (B).pdf` (291 KB) | 2026-03-24 |
| Electrical/ | `6367-E20 (3).pdf` (442 KB) | 2026-03-24 |
| Landscape-and-Hydraulic/ | `7295_NB_LA_ST2_COMBINED.pdf` (16.4 MB) | 2026-03-24 |
| Structural/ | `7295_Structural Combined_Latest.pdf` (22.9 MB) | 2026-03-24 |
| Structural/ | `Crane Placement.pdf` (2.5 MB) | 2026-03-24 |
| Variation-Stairs/ | `6367_Repair Drawings_A.pdf` (650 KB) | 2026-04-10 |

## Blind comparison context
- Session UUID: `e57c7d98-c90d-48ed-b874-23bf35f19be8`
- Comparator: Hasibul Khan (prior 2630 pricing — friend-vault, off-limits)
- New pricer: claude-code-opsman + Rocky McLoughlin
- Path exclusions in force: any local `*hus*2630*` / `*quote*` / `*price*` / `*_v-CW*` 2630 filename + entire friend-vault path
- Methodology quarantine: 0 rows (narrow interpretation; broader interpretation pending Rocky decision — see audit trail md)
- Audit trail: `_Internal/audit-trail/session-e57c7d98-c90d-48ed-b874-23bf35f19be8.md`

## What we still need
- Bid due date (RFI to Rocky)
- BOQ from TCE if they're providing one — none in current inbound (would land in `02b - BOQ and Rate Schedules/`)
- RFQ scope email — none in current inbound (would land in `06a - Emails/`)
- Confirm scope boundary: full seawall structure, or specific package? Concrete + steel-fixing + formwork only, or full civils?

## Next steps (NOT started — Rocky-gated)
1. Drawing extract (text pass) on the 7295 + 6367 packs → Drawing-Index.md + Drawing Elements
2. BOQ parse (if BOQ supplied) or quantities-takeoff from drawings
3. Run `lfcs-bid-prep-doc` to draft `00-Bid-Prep.md`
4. Run `lfcs-pre-grill` (Phase 0) — MANDATORY before pricing
5. First-pass pricing
6. Seal pre-comparison reasoning to BCS row
7. Reveal phase + corrections capture