scope: Stair Flight (2 stringer + 3 risers, in-situ concrete)
unit: per flight
total_per_unit: 5610
labour_rate_basis: $85/hr ordinary (Rate Card V1.7)
source_job: Solutions Plus Field of Play Hornsby
source_file: Rates/FRP Rates Development.xlsx — sheet "Sol+ Hornsby Stairs"
source_vault: Hasibul Khan / LFCS Obsidian Vault / 08 - Rates/FRP Rates Development.md
last_updated: 2026-05-06
tags: [scope-benchmark, stair, flight, in-situ, frp]
---

# Stair Flight — 2 stringer + 3 risers (in-situ)

**Total per flight: $5,610** (ordinary labour basis)

## Buildup

| Task | Crew | Hours | Rate | Cost |
|---|---|---|---|---|
| Site prep / markout | — | 20 hrs | — | (rolled in below) |
| 2 lads stringer + 3 risers (5 hrs) | 2 | 10 hrs | $85 | $850 |
| 1 lad bench, 10 risers (4 hrs) | 1 | 4 hrs | $85 | $340 |
| 2 lads steel (5 hrs) | 2 | 10 hrs | $85 | $850 |
| Finish risers, 2 lads (4 hrs) | 2 | 8 hrs | $85 | $680 |
| Pour, 2 lads (1 day) | 2 | 20 hrs | $85 | $1,700 |
| Strip, 2 lads (5 hrs) | 2 | 10 hrs | $85 | $850 |
| Prelims and Margin | — | 4 hrs | $85 | $340 |
| **Total per flight** | | | | **$5,610** |

## Productivity calibration

- Use **as-is** for similar 3-riser flights with stringer formwork, day shift
- **Scale linearly** for additional risers (~$X per riser — derive from the bench-risers line: 4 hrs / 10 risers = 0.4 hrs/riser × $85 = $34/riser, plus pour/strip overhead)
- **+30%** if formwork is tight-access (single side access) or finish is exposed-architectural
- Stairs at $5,610 per flight — useful benchmark for future stair scopes

## Notes

- Markout time (20 hrs) is rolled into the build labour, not separately invoiced
- "Bench, 10 risers" = bench-style stair build for the riser fronts (4 hrs for 10 risers efficiency)
- Includes: form + reo + pour + finish + strip
- Excludes: reo supply, concrete supply, handrail (separate scope)

## Cross-reference

- [[../pricing-checklist]] Phase 4
- Solutions Plus jobs (Hornsby + others) — likely candidate

## Source

Adapted from Hasibul Khan's `08 - Rates/FRP Rates Development.md` (sheet "Sol+ Hornsby Stairs"), accessed read-only via Drive shortcut on 2026-05-06.