# LFCS Daily Site Notes — 2026-05-11

## TCE Liverpool

**Job:** TCA — Liverpool, NSW
**Crew:** Donald Murphy (boss), Steve (steel), 1 apprentice, 1 labourer
**Hours:** 7:00am – 3:30pm (8 hrs)

### Timeline
- **07:00** — Crew on site. Ground workers not ready. LFCS held up.
- **~08:30** — Rebar mat tied, raked square to keep shape when lifting. Ready at 8:30am (2 men). Steel mat laid out but not tied. Waiting on ground workers to finish before dropping in.
- **~09:30** — Heavy rain starts. Crew knocked off for breakfast.
- **~10:15** — Came back after rain. Finished rebar mat prep (45min, 2 men).
- **11:01am** — Ground workers nowhere near ready. **TCE foreman confirmed LFCS on DAYWORKS for the day.** (Critical — delay formally acknowledged by client.)
- **12:07pm** — First back shutter completed (2 men, 1hr).
- **1:22pm** — Apprentice drilling started. Ground workers still on lunch. LFCS held up — 2nd major delay of the day.
- **1:24pm** — Last external shutter in progress (2 men). 3rd outside shutter done.
- **2:22pm** — 3rd outside shutter completed.
- **2:55pm** — Ground workers finally finished.
- **1:25pm** — Donald on internals (1 man). Extra timber cutting required — ground workers under-dug by 300mm. Working room behind shutters 60mm in places (standard 600mm). Extra labour not in scope.
- **3:30pm** — Finished.

### Photos
_(saved to daily folder — see filenames below)_

- `2026-05-11_liverpool_01.jpg` — Site overview, ground workers active
- `img_7bc5bb80c57c.jpg` — Plywood platform / walkway
- `img_0d286d2b21cc.jpg` — Ground workers, blue paint markings, sand soil
- `img_2450c72825ad.jpg` — Timber formwork, power tool, panels
- `img_b2f6a1092586.jpg` — Concrete slabs, compactor, ground workers
- `img_7e9ed1f4f200.jpg` — Timber formwork panels, yellow cord
- `img_183759d68c47.jpg` — Worker on ground, yellow cord, measuring
- `img_72a8b7dcfff4.jpg` — Rebar grid, wooden supports, surveyor instrument
- `img_a4cea338634f.jpg` — Rebar mat, concrete, drainage pipe
- `img_e6918f4a6414.jpg` — Shipping container, vertical planks, board propped
- `img_58001af2fa09.jpg` — Shuttering panels, timber beams, orange vest worker
- `img_0cc93c6d3e61.jpg` — Trench/excavation, drainage pipe, concrete, "Mario"标记
- `img_514f7a5e6166.jpg` — Ground works, sandy soil, concrete, rebar, blue markings

### Flags / Variation Claims
- ✅ **Dayworks confirmed by TCE foreman at 11:01am** — delay formally acknowledged
- ⚠️ 3hr morning hold (07:00–10:15) — dayworks
- ⚠️ Rain delay ~45min
- ⚠️ 2nd hold post-lunch (12:30–1:22pm) — ground workers on lunch
- ⚠️ Clearance shortfall variation — ground workers under-dug by 300mm, working room 60mm vs standard 600mm
- ⚠️ Extra timber cutting not in scope

### P&L Question
_Dayworks confirmed — so time is covered. Was the variation for the clearance shortfall and extra timber cutting also agreed verbally, or is that still to be claimed?_

### Action
- Get job number from Liam
- Send written delay notification to TCE foreman (email or SMS) confirming delays even though dayworks was agreed — protects variation claims for clearance shortfall and extra timber cutting