
## Override None — 2026-05-07T14:55:53+00:00
- session_ref: `ce4100f9-9176-4a93-87ee-01e6d05674f6`
- bid_line_item: ['recDUMMYBLI14ce4317']
- original_rate_ex_gst: 19400.0
- override_rate_ex_gst: 0.0
- reason_codes: ['BOILERPLATE-CARRY']
- reviewer_type: Trades-Internal-Rocky
- reviewer_name: Rocky
- free_text_rationale: Hammond Canal is LAKE, not seawater, not tidal. Q-G7 grill answer overrides boilerplate 5% saltwater uplift carried over from coastal precedent.

## Override None — 2026-05-07T14:55:53+00:00
- session_ref: `ce4100f9-9176-4a93-87ee-01e6d05674f6`
- bid_line_item: ['recDUMMYBLIdc3ffcc3']
- original_rate_ex_gst: 11500.0
- override_rate_ex_gst: 0.0
- reason_codes: ['STRUCTURAL-DEDUCT', 'SCOPE-SHIFT']
- reviewer_type: Trades-Internal-Rocky
- reviewer_name: Rocky
- free_text_rationale: Concrete pumps + EWP excluded per LFCS standing FRP scope. Direct $11,500; lump $12,880 after prelim+margin removal. Per Stage 2 § 2.7 STANDING-SCOPE CORRECTION.

## Override None — 2026-05-07T14:55:53+00:00
- session_ref: `ce4100f9-9176-4a93-87ee-01e6d05674f6`
- bid_line_item: ['recDUMMYBLIe1ac0585']
- original_rate_ex_gst: 5000.0
- override_rate_ex_gst: 5000.0
- reason_codes: ['POSTURE-MISMATCH']
- reviewer_type: Trades-Internal-Liam
- reviewer_name: Liam
- free_text_rationale: Variation rate-card shows $98/hr trade vs $85/hr submission, $108/hr supervisor vs $95, materials cost+12.5% vs +10%. Defensible-for-variations posture broken. Pre-Pricing-Grill Q-F1 said defensible — lock variation rates to submission rates.
