## Override None — 2026-05-07T14:55:53+00:00
- session_ref: `fd78911c-8de9-4b15-af1c-b6964d2e9a92`
- bid_line_item: ['recDUMMYBLI9c513036']
- original_rate_ex_gst: 0.0
- override_rate_ex_gst: 14611.0
- reason_codes: ['STRUCTURAL-ADD']
- reviewer_type: Trades-Internal-Liam
- reviewer_name: Liam
- free_text_rationale: Added diaphragm beams at the abutments — missing from HC pricing schedule. 3 lines: $11,094 formwork + $3,046 reo + $470 concrete.

## Override None — 2026-05-07T14:55:53+00:00
- session_ref: `fd78911c-8de9-4b15-af1c-b6964d2e9a92`
- bid_line_item: ['recDUMMYBLI9bfe1ac4']
- original_rate_ex_gst: 0.0
- override_rate_ex_gst: 9000.0
- reason_codes: ['SCOPE-SHIFT', 'POSTURE-MISMATCH']
- reviewer_type: Trades-Internal-Liam
- reviewer_name: Liam
- free_text_rationale: Rate Only line for bridge edge protection hire beyond 6-week base period. Hire-duration assumption clause inserted in Detailed Assumptions.

## Override None — 2026-05-07T14:55:53+00:00
- session_ref: `fd78911c-8de9-4b15-af1c-b6964d2e9a92`
- bid_line_item: ['recDUMMYBLI83a5ddb0']
- original_rate_ex_gst: 0.0
- override_rate_ex_gst: 0.0
- reason_codes: ['SCOPE-SHIFT', 'POSTURE-MISMATCH']
- reviewer_type: Trades-Internal-Liam
- reviewer_name: Liam
- free_text_rationale: Cranage delineation explicit per HCB pattern: HC supplies for super-T launches; LFCS supplies for parapet lifts. #1 source of bridge-job disputes — never leave ambiguous.