job_no: 2627
job_name: Airey Park — Homebush West
purpose: Internal-only exclusions list. Three-tier 2629 shape. Worker layers bid-specific exclusions on top of this skeleton.
session_id: d58cec3f-9794-4dbf-8976-47b8c893eaab
date: 2026-05-08
authored_by: claude-code-orchestrator
NOT_FOR_EXTERNAL_DISTRIBUTION: true
sanitisation: NOT_REQUIRED (internal-only artefact; sanitisation runs on the customer-facing PDF derived from this)
revision: 2 (worker carve-outs from Phase 3 first-pass layered onto skeleton)
revision_authored_by: lfcs-pricing
revision_date: 2026-05-08
revision_session_id: 80b1f893-d887-4130-b96f-dd48d5450edd
methodology_source: Standard LFCS Exclusions Library v1 (orchestrator standards/Standard-LFCS-Exclusions-Library.md)
---

# 2627 — Clarification & Exclusions (skeleton)

## 2627-specific overrides applied this revision

These deviate from Standard. Confirmed at Phase 1 intake gate (assumptions-log-2627.md).

| Standard | 2627 override | Reason |
|---|---|---|
| Labour: direct × 1.10 cont × 1.15 margin = 1.265 | **Labour: direct × 1.15 cont × 1.15 margin = 1.3225** | Rocky 2026-05-08 — drawings rev D pre-IFC, full pre-IFC posture |
| Materials: direct × 1.15 margin × 1.10 cont = 1.265 | **Materials: direct × 1.15 margin × 1.15 cont = 1.3225** | Orchestrator-applied parallel uplift; flagged for Rocky review at sanity-check |
| Concrete grade per element schedule | **32 MPa all elements** (footings + slab on ground + pathway slab + drop edge beams) | STR25020 S100/S200 concrete quality table |

(Worker may add overrides in Phase 3 first-pass take-off; Rocky reviews in Phase 4 sanity-check.)

---

## Standard Exclusions (1–10)

LFCS scope is consistently narrow across all jobs: formwork supply+install+strip, steel fix only, concrete place+finish only, curing supply+place. Standard items always excluded:

1. Surface water / groundwater management, dewatering, disposal
2. Disposal of waste off-site
3. Latent conditions
4. Asbestos / contaminated material handling
5. D&C (design-and-construct) responsibility
6. Permits of any kind
7. Delays caused by other trades or Head Contractor (variation at day-labour rates)
8. Service locating, protection, relocation
9. Slip testing, coatings, sealants beyond 20mm chamfers + AS3610.1 Class B finish
10. Engineering certifications beyond what the contract documents nominate to LFCS

---

## Preliminaries — Head Contractor provides (11–28)

11. Site facilities and compounds
12. Traffic management, safety barriers, Section 138 application, traffic-control plans, spotters
13. Access to construction area
14. Surveys, setting-out, datum points, registered surveyor (per drawings note 9 S100 + S200 "refer to architectural drawings for all setout, levels, falls etc.")
15. Geotechnical investigation + testing (per drawings note 1 — geotech ref "S2348_GL_02_Rev0" by HC)
16. Environmental permits and approvals
17. Site management plan + ESCP + dust + noise monitoring
18. All bulk earthworks — excavation, backfill, compaction, sub-base, fill, lean-mix blinding placement (drawings note 5 S000 — "50mm minimum blinding layer should be applied to the base of all foundations" — placement by earthworks sub; LFCS uses but does not place)
19. All plant — cranage, concrete pumps, concrete trucks, telehandlers, forklifts, excavators, generators, site power
20. Concrete supply (32 MPa, 80mm slump, 20mm max aggregate, Cement Type A, AS1379 dockets per truck)
21. Reinforcement supply (Grade 500N N12/N16, mesh SL82 T&B, tie wire delivered with steel)
22. Cast-in items supply (anchor bolts, base plates, lifting inserts, conduits, sleeves, drainage outlets)
23. Hilti / chemical anchor cartridge supply (HIT-RE 500 V4, HIT-HY 200 — LFCS installs if scoped)
24. Joint material supply (10mm polythene isolation joint material, sealants, backing rods per S200 KJ + SJ details)
25. HDPE vapour proof membrane supply (drawings S200 typical drop edge beam DEB1 detail — "continuous vapour proof membrane over 50mm sand bedding")
26. Site amenities, sheds, toilets, skip bins, bin lifts
27. Vibration monitoring (equipment + recording — if any vibration risk near existing structure)
28. Concrete testing — NATA lab cylinders + slump tests + dockets per truck (LFCS makes cylinders + delivers; HC pays NATA per pavement spec §14)

---

## Detailed Exclusions, Assumptions & Inclusions (29+)

### Exclusions

29. All bulk earthworks (excavation, backfill, compaction, lean-mix blinding placement) — by earthworks sub
30. Steel screw piles, bored piles, driven piles — by piling sub (drawings S100 + S200 note "PIERING MAY BE REQUIRED. ENGINEER TO CONFIRM DURING CONSTRUCTION" — pier scope is variation if confirmed)
31. Triton mattresses (geofabric) — n/a (no marine works)
32. Shotcrete application — n/a
33. Demolition (including local removal of existing wall below to accommodate concrete riser per S200 note) — by demolition sub
34. Precast supply — n/a (sandstone retaining wall blocks supplied by HC per S51 detail; LFCS does NOT lay)
35. Precast install (lift, place, level, set, brace) — n/a
36. Precast bedding anchors — n/a
37. Connection or fixing TO precast — n/a
38. Stainless steel handrails — by metalwork sub (per drawings — handrails on seating terrace)
39. Hydraulic / plumbing fixtures — by hydraulics sub
40. Mechanical, Electrical, Hydraulic, Fire, P&ID work — by MEPF subs
41. Landscape (planting + softworks + hardworks + furniture + signage + paving units laid as units + brick edge supply + line marking + kerb + gutter beyond LFCS in-situ pavement scope) — by landscape sub
42. Waterproofing trades (FRC sheet, bitumen paint, polyurethane coatings, sealing per drawings S200 note 6 — "ALL EXPOSED SLAB TO BE WATERPROOFED BY APPROVED SYSTEM") — by waterproofing sub
43. Masonry / blockwork / brickwork — 190mm block walls + brick walls per S100 + S200 — by masonry sub
44. **Sandstone block retaining wall** (300×300×1000 long blocks per S51 detail) — supply + place by masonry / specialist sub. LFCS does NOT lay.
45. **Brick walls** (per S100 brick wall above + S200 typical brick wall) — by masonry sub
46. **Block walls** (190mm block above + below per S100 + S200) — by masonry sub
47. Falsework engineering temp works design + verifications — by HC's structural engineer
48. Bypass pumping / temporary stormwater diversion — by HC
49. Out-of-hours, weekend, night-shift work — variation at LFCS Rate Card V1.7 night/weekend loading
50. NCRs, defects, rework arising from drawing variation post-current-rev-D — variation
51. Confined space entry, hazardous area certifications, biohazard PPE — variation
52. Cancellation premium (minimum 8 hrs charged per Rate Card V1.7) — noted
53. **Quantities provisional ±20-30%** subject to receipt of architectural setout drawings (drawings note 9 S100 + S200 "REFER TO ARCHITECTURAL DRAWINGS FOR ALL SETOUT, LEVELS, FALLS ETC." — architectural set NOT supplied in inbound drawing pack rev D). Final price subject to confirmed quantities; quoted total derives from visually-scaled provisional quantities against grid spacing.
54. **Density coring 75-100 mm Ø within 2 days** per pavement spec §14.2.5 — destructive testing taken by NATA lab; **HC pays for core repair** (drill-hole patch + bond agent + epoxy fill). LFCS not responsible for core repair cost or labour.
55. **Late-afternoon pour saw-cut window** — sawn control joints must be cut within 24 hrs of pour per pavement spec §11.3.6 + S200 SJ detail. If 24-hr saw-cut window forces off-hours work (early evening, late night, weekend), variation at LFCS Rate Card V1.7 night/weekend loading (8-hr minimum charge per item 52). LFCS programmes pours to allow standard-hours saw-cut where feasible; HC programme constraints that force late-afternoon pours = variation.
56. **Concrete grade conflict 32 vs 35 MPa for 125mm pathway slab** — drawings rev D S100/S200 concrete quality table specifies 32 MPa; pavement spec P171342-SP-001-0 Table 1 specifies 35 MPa compressive + 4.5 MPa flexural for "pavement Base" element. RFI required for designer clarification. **LFCS placing labour unaffected by grade**; HC concrete-supply line absorbs supply-cost premium (~$300 across 15 m³ pathway). LFCS not responsible for grade-clarification delay if RFI unanswered.
57. **Pavement spec template carry-over** — pavement spec P171342-SP-001-0 §1 Introduction references "St Ives Showgrounds proposed carpark development" (different project). Substantive clauses §4–§15 generic and applied as relevant. RFI flagged for designer confirmation; bid relies on substantive clauses regardless. No pricing adjustment.
58. **Flexural beam testing per pavement spec §14** — LFCS makes + delivers beams; NATA flexural lab cost via HC (per item 28). Designer to confirm flexural retention for pedestrian-load pathway (more typical for heavy-vehicle pavement). Possible scope reduction if flexural waived.

### Assumptions

A1. **Concrete grade 32 MPa** all elements per STR25020 S100 + S200 concrete quality tables. (Supersedes any earlier 25 MPa indication.)
A2. **Working hours** 7:00 am – 3:30 pm Mon–Fri unless HC instructs otherwise.
A3. **Programme** TBD (to be confirmed by HC at RFQ stage). Rates assume a continuous run; broken programme = variation at day labour.
A4. **Drawings rev D** — current rev. Worker to flag any post-rev-D updates at Phase 3.
A5. **Site classification AS2870 Class H1**, bearing 210 kPa stiff clay (per drawings note 1 + geotech S2348_GL_02_Rev0). LFCS not responsible for verifying bearing capacity (item 14 above).
A6. **Saw-cut joint timing** — within 24 hours of pour per S200 SJ detail.
A7. **Curing** — polythene + hessian per pavement spec §10. **7-day cure** per pavement spec §10.1.1 minimum (corrected from 14 days at revision 1; pavement spec wins by precedence).
A8. **Productivity** — pavement scope assumed at 160 m²/day (industry standard for in-situ concrete pavement); footings + slabs assumed at standard LFCS rate-card output, with productivity adjustments per A10–A12 below.
A9. **Adverse weather** — excluded; variation at day-labour rates per item 7.
A10. **Existing-slab interface productivity reduction 15-20%** built into per-line rates for tooth slab + tooth stair into existing slab/brick wall + drill+epoxy N12-400 dowels + local wall-removal coordination (drawings S201 sections 1+2 + S200 typ toothing detail). LFCS not responsible for unforeseen interface conditions beyond what is shown on drawings rev D — any additional dowel / waterproofing / patching arising from existing-structure conditions revealed during construction is variation.
A11. **DEB1 deep-edge-beam productivity reduction 30%** built into formwork + reo + place rate (1200 deep × 300 thick × 13 lin m; multi-layer cage; tremie place; heavy props). LFCS not responsible for delays caused by DEB1 prop-removal cylinder-test timing per S000 concrete note 9 (28-day OR 14-day-with-cylinder-test gates prop removal; if HC's NATA cylinder testing programme delays prop removal, standing time is variation).
A12. **Stepped SF1 seating terrace productivity reduction 10-15%** built into rate (3 stepped lifts per S51).

### Inclusions (LFCS supplies)

I1. Plastic spacers (no metal chairs — galvanic corrosion)
I2. Polythene + hessian curing for 7-day cure (per A7 corrected)
I3. Formwork ply + timbers + props (assumed LFCS-supplied unless drawings note TCE-supplied — confirm at Phase 0 grill Q-A3)
I4. Diamond saw + dust suppression for joint forming
I5. Megapoxy bonding agent (rare; usually TCE — flag if drawings spec'd)
I6. Concrete pumping vibration ONLY where LFCS placing crew runs the vibrator (pump itself by HC per item 19 above)

---

## Worker layered carve-outs (Phase 3 first-pass output — revision 2)

Layered by `lfcs-pricing` 2026-05-08 from `2627-First-Pass-Priced-TakeOff-2026-05-08.md` per §4.5 spec. Items merged inline above:

| Section | Items added/changed | Source |
|---|---|---|
| Assumptions | A7 corrected (14→7 day cure) | pavement spec §10.1.1 |
| Assumptions | A10 (NEW) — existing-slab interface productivity reduction 15-20% | drawings S201 + S200 + take-off F5 flag |
| Assumptions | A11 (NEW) — DEB1 deep-edge-beam productivity reduction 30% + prop-removal-test variation carve-out | drawings S200 + spec §6.5.1 + S000 note 9 + take-off F6 flag |
| Assumptions | A12 (NEW) — stepped SF1 seating terrace productivity reduction 10-15% | drawings S51 + take-off |
| Inclusions | I2 corrected (7-day cure) | A7 alignment |
| Detailed Excl | 53 (NEW) — quantities provisional ±20-30% subject to architectural setout RFI | take-off F3 flag + drawings note 9 |
| Detailed Excl | 54 (NEW) — density coring core-repair cost via HC | pavement spec §14.2.5 |
| Detailed Excl | 55 (NEW) — late-afternoon saw-cut off-hours premium variation | pavement spec §11.3.6 + S200 SJ + take-off F7 flag |
| Detailed Excl | 56 (NEW) — concrete grade 32 vs 35 MPa pathway RFI carve-out | drawings S100/S200 vs pavement spec Table 1 + take-off F1 flag |
| Detailed Excl | 57 (NEW) — pavement spec template carry-over RFI carve-out | pavement spec §1 St Ives reference + take-off F2 flag |
| Detailed Excl | 58 (NEW) — flexural beam testing scope clarification | pavement spec §14 + take-off F10 flag |

---

## Three-tier shape (preserved per 2629 canonical)

For downstream conversion to customer-facing PDF (Liam-authored letter or BoQ-response):

- **Tier 1 — STANDARD** (items 1–10 + 11–28) — Standard LFCS Exclusions Library v1; appears verbatim in customer-facing exclusions section (boilerplate)
- **Tier 2 — PRELIMINARIES** (items 11–28 dual-listed) — overlaps with Standard; HC-provided items typically appear as "Preliminaries by HC"
- **Tier 3 — DETAILED-EXCLUSIONS-ASSUMPTIONS-INCLUSIONS** (items 29-58 + A1-A12 + I1-I6) — bid-specific carve-outs derived from drawings + spec + take-off

Customer-facing PDF derives from this internal three-tier doc with sanitisation pass per `lfcs-pricing-agent` §4.3 (L1 strips `_internal_*` + agent metadata; L2 verifies independent + human-gated before send).

---

## Format note

Customer-facing PDF derives from this internal three-tier doc with sanitisation pass per `lfcs-pricing-agent` §4.3. L1 + L2 sanitisation removes `_internal_` notes + agent metadata before Rocky-authorised send.

## Revision history

| Rev | Date | Author | Changes |
|---|---|---|---|
| 1 | 2026-05-08 | claude-code-orchestrator | Skeleton; standing-context overrides applied; intake-locked envelope mirrored |
| 2 | 2026-05-08 | lfcs-pricing | Worker layered carve-outs: A7 corrected; A10–A12 new; I2 corrected; Detailed Excl 53–58 new |