# Work Log — Week 6 (3 Feb – 9 Feb 2026)

**Employee:** Michael (Rocky) McLoughlin
**Project:** Ford Civil, Parramatta
**Company:** LF Construction Services

| Day | Date | Start | Finish | Lunch | Hours | Description |
|-----|------|-------|--------|-------|-------|-------------|
| Mon | 3 Feb | — | — | — | 8 | Take out of hours owed |
| Tue | 4 Feb | — | — | — | 8 | Take out of hours owed |
| Wed | 5 Feb | 7:00am | 4:30pm | 30 min | 9 | All cages in. 2 cages to be altered — surveyor gave wrong marks. |
| Thu | 6 Feb | 7:00am | 4:30pm | 30 min | 9 | Fixed steel in 3 (wrong heights). Fixed conduits in 2 (plumber pipes too far in). Formed 2 shutters. Poured concrete. Tidied up, loaded ute. |
| Fri | 7 Feb | — | — | — | 8 | Take out of hours owed |

**Total: 42 hours**

## Daily Notes

### Wednesday 5 Feb
- Morning delayed — no edge of kerb from groundworks, got going ~8:30am
- Struck 3 pedestals with holding down bolts while waiting
- Engineers gave wrong heights ~10:48am — all morning work redone
- All cages in by end of day
- 2 cages need altering (wrong marks)
- **Tomorrow:** Get material, build 2 shutters, position conduits on last 2, drop 2 links, cut 8 bars. Concrete at 11am.

### Thursday 6 Feb
- Fixed steel in 3 bollards — surveyor gave wrong heights the day before
- Fixed conduits in 2 — plumber's pipes coming too far in, bend too steep
- Formed up 2 shutters, set the heights
- Set conduits coming out at 225mm from back of kerb
- Concrete landed, poured, finished concrete
- Washed tools, lunch
- Came back, tidied area
- Loaded ute with strips of tin and little pedestals
- 7:00am – 4:30pm, 30 min break, 9 hours