# Work Log — Week 7 (10 Feb – 16 Feb 2026)

**Employee:** Michael (Rocky) McLoughlin
**Project:** 69 Phillip St, Parramatta
**Company:** LF Construction Services

| Day | Date | Start | Finish | Lunch | Hours | Description |
|-----|------|-------|--------|-------|-------|-------------|
| Mon | 10 Feb | | | | | |
| Tue | 11 Feb | | | | | |
| Wed | 12 Feb | 7:00am | 4:30pm | None | 9.5 | Moved edge boards (surveyor marks wrong). Fixed pit box-out. Installed mesh, checked cover. Waiting on falls info. Concrete pour — racing the rain. |
| Thu | 13 Feb | 7:00am | 4:00pm | None | 9 | Steel stop ends, Z-bars installed, control joints cut, expansion joints between pillars. Snagged pour, concrete poured. Surveyor marked other end. |
| Fri | 14 Feb | 7:00am | 1:00pm | None | 8 | Edge board with full crew. Control joints, bitumen board, stop ends prep for Monday pour. |

| Mon | 16 Feb | 7:00am | 4:00pm | None | 10 | Footpath area — mesh for slab thickenings, edge boards, stop ends, box-outs. Slab prep & cleanup for concrete. |

**Total: 36.5 hours (so far)**