# Arncliffe — Ford Civil

**Project:** Ford Civil, Parramatta (working at Arncliffe site)
**Client/Builder:** Ford Civil
**Started:** Week of 27 Jan 2026

## People

| Role | Name | Notes |
|------|------|-------|
| Foreman | ? (new) | Started recently |
| Engineer | ? | Gave wrong heights 5 Feb |
| Supervisor | Hass/Huss | Gave them the bollards job |
| Crew | Rocky (Michael) | Supervisor (steelfixer background) |
| Crew | Mike | Steel fixer, working with Rocky |

## Work History

### Week 5 (26 Jan – 2 Feb)
- Steel fixing & shuttering
- Wed & Thu only (Mon holiday, Tue & Fri off)

### Week 6 (3 Feb – 9 Feb)
- **Wed 5 Feb:** All cages in. 2 cages need altering (surveyor wrong marks). Engineers gave wrong heights — morning rework.
- **Thu 6 Feb:** Fixed steel in 3 (wrong heights). Fixed conduits in 2 (plumber pipes). Formed 2 shutters. Concrete poured. Tidied, loaded ute. 9 hrs.uild 2 shutters, position conduits on last 2, drop 2 links, cut 8 bars. Concrete at 11am.

## Site Notes
- Groundworks crew sometimes slow to provide edge of kerb
- Engineer has given wrong marks twice (heights on 5 Feb, 2 cages)