# AM Look-Ahead — 2026-06-05 — Hornsby (01-2275)

## What happened

Cron ran at ~6am Fri 5 Jun 2026. Active job: Hornsby (01-2275 HPE Field of Play).

**Key findings from file reads:**

| File | Ongoing copy | Upcoming copy | Decision |
|---|---|---|---|
| `programme-24wk.md` | 4 lines (header only) | 57 lines full table | Used Upcoming |
| `_REGISTER.md` | 4 lines (header only) | 84 lines, 33 RFIs | Used Upcoming |
| `Job-Tracker.md` | 15 lines, all empty | 58 lines, all empty | Both empty |
| `_subbie-schedule.md` | N/A | header only, no bookings | Empty |

**Today's programme (Wk 6, from Upcoming):** EA Zone 3 — 4 pours × 160 m² + 122 m² balance = 722 m². EA complete target Sat 6 Jun. Claim 1 was due 25 May (11 days overdue).

**RFI status:** All 10 Cat A still show `Sent` / `Pending` — no Date In on any of them. RFI-A1 (sub-base handover) was due 15 May — already 3 weeks past deadline.

## The two new lessons encoded in the skill

1. **Empty Job Tracker + no diary at Week 6 = operational gap, flag hard.** Not "confirm with Rocky" as a soft note — report it as a standalone finding: "Job Tracker empty — 5 weeks in, zero hours captured." Claims are indefensible without this.

2. **Programme week row ≠ confirmed site activity.** The programme said Week 6 EA Zone 3 pours. The Job Tracker and diary were both empty. This could mean: (a) work is happening but not captured, (b) work hasn't started, or (c) the programme is ahead of actual progress. Report the discrepancy explicitly.

## Telegram output delivered

```
Hornsy AM look-ahead — Fri 5 Jun

Today: Wk 6 pours continue (EA Zone 3, ~722m² target, ~360m² done this wk).
No diary entry yet for past weeks — Job Tracker empty.

Blockers: Sub-base S/SE still not certified (deadline was 15 May).
HammerTech induction must be done before crew foot on site.
All 10 Cat A RFIs still pending with Joel — chase him today.

RFIs to chase: A1 sub-base cert · A3 pump · A4 plant · A5 mix designs · A8 HammerTech slot.

Claim 1 ($25–35K) is 11 days overdue — submit today.

No subbies booked. No deliveries recorded today.
```

## Vault diary written

`/home/ccuser/opsman-work/Jobs/Ongoing Jobs/01-2275 - HPE Field of Play Hornsby/07 - Site Documents/07d - Daily Diary/2026-06-05.md` — appended AM look-ahead entry.

## Status: Ongoing Jobs folder is a skeleton

Ongoing copy had correct folder structure but all files were minimal. Upcoming copy had rich data. This is the expected Hornsby pattern — the job was set up in Upcoming with full docs, then a skeleton was created in Ongoing (likely when site started) without copying the full programme/RFI register across.

**Pattern confirmed again (2026-06-05):** Always cross-reference Ongoing vs Upcoming. Never assume the sparse copy is the authoritative one.