# HPE Field of Play Hornsby — Look-Ahead 2026-05-21

**Date:** Thu 21 May 2026 | **Week:** Wk 4 (18–23 May) | **Cron run:** 06:00

## Job state

- Job: 01-2275 HPE Field of Play Hornsby
- Status: ongoing, start_date 2026-04-30 (22 days in)
- Type: hybrid (price + dayworks)
- Programme row: EA Zone 1 — 5 pours × 160 m² = 800 m² exposed aggregate. Wash + cure each panel D+1.

## File audit

| Path | Lines | State |
|---|---|---|
| `Ongoing/.../00-brief.md` | 13 | ✅ present |
| `Ongoing/.../Job-Tracker.md` | 15 | ⚠️ header only, 0 hours, 0 materials |
| `Ongoing/.../04 - Programme/programme-24wk.md` | 4 | ⚠️ header only — EMPTY table |
| `Ongoing/.../06b - RFIs/_REGISTER.md` | 4 | ⚠️ header only — no RFIs logged |
| `Ongoing/.../07d - Daily Diary/` | — | ❌ directory empty, no entries |
| `Ongoing/.../07a - Dockets/` | — | ❌ no dockets ever |
| `Upcoming/.../04 - Programme/programme-24wk.md` | 57 | ✅ full 24-wk table |
| `Upcoming/.../06b - RFIs/_REGISTER.md` | 84 | ✅ full 33-RFI register |
| `Upcoming/.../10 - Subcontractors/_subbie-schedule.md` | 33 | ✅ present, empty |
| `Upcoming/.../Job-Tracker.md` | 58 | ✅ present, 0 hours |

**Pattern:** Ongoing copy is sparse (4-line programme, no RFIs). Upcoming copy has the full programme and RFI register. Hornsby is Ghost Job Variant B — operationally active but Ongoing folder was never populated with OpsMan's captures.

## RFIs

10× Cat A RFIs sent 29/04/26 — all still **Pending**. No written responses received. Mobilisation blockers unresolved 3 weeks in.

Key blockers for today's pour:
- RFI-A1: S/SE sub-base certified handover
- RFI-A2: Survey + set-out responsibility
- RFI-A3: Concrete pump booking
- RFI-A4: Batching plant nomination
- RFI-A5: Mix designs
- RFI-A8: HammerTech induction slots
- RFI-A9: Steel delivery + laydown
- RFI-A10: Blinding layer in S/SE zone

## Subbies / Deliveries

Nothing booked. Pump TBC per RFI-A3. Steel TBC per RFI-A9.

## AM output delivered

```
LFCS — Hornsby AM Look-Ahead | 21 May 2026 | Wk 4 (18–23 May)

Today: EA Zone 1 — 5 pours × 160 m² = 800 m². No diary entries yet for this week.

⚠️ Blockers: 10× Cat A RFIs sent 29 Apr — all Pending. Mobilisation still unresolved.

📌 Chase: All 10 Cat A responses from Joel Alvey / Solutions Plus.
📦 Deliveries: Steel TBC (RFI-A9), pump TBC (RFI-A3).
```

## Action

Rocky must chase Joel Alvey for all 10 Cat A responses. Without written answers, pre-pour checks cannot be confirmed satisfied. Programme is at risk — 22 days in, EA Zone 1 should be underway.