# TCE Liverpool — 2026-05-11 Site Report (Draft)

**Status:** Pending job number (TCE Liverpool, dayworks, site at Liverpool NSW)
**Compiled by:** Hermes from Telegram updates

---

## 07:00 — Crew on site
- Ground workers not ready. LFCS held up.

## 09:30 — Heavy rain
- Crew knocked off for breakfast.

## ~10:15 — Back to work
- Rebar mat tied and ready (2 men, 45 min)
- Steel mat laid out but not tied. Ready at 8:30am.

## 12:07 — First back shutter completed (2 men)

## 12:30–1:22pm — Apprentice drilling started
- Ground workers still not finished — on lunch. LFCS held up (2nd major delay).

## 1:24pm — Last external shutter in progress (2 men)
- 3rd outside shutter done.

## 1:25pm — Donald on internals (1 man)
- Additional timber cutting required — ground workers under-dug by 300mm in places.
- Working room behind shutters: 60mm in places. Standard practice: 600mm minimum.
- Extra labor time not in original scope — variation flag.

## 3:30pm — Finished
- Total hours: 7am–3:30pm = **8 hrs**

---

## Delay / Variation Summary

| Time | Event | Flag |
|---|---|---|
| 07:00–09:30 | 3hr morning hold — ground workers not ready | Billable idle |
| 09:30 | Rain delay ~45min | Weather variation |
| 12:30–1:22pm | 2nd hold post-lunch — ground workers still not finished | Billable idle |
| Throughout | 60mm clearance behind shutters (should be 600mm) | Scope variation |

**Notifications:** Verbal to TCE foreman by Donal. Written record via SMS/WhatsApp recommended before docket sign-off.

---

## Photos (6 total)
(Sourced from Telegram, captions by Rocky)

1. Steel mat, tied, raked square to keep shape when lifting. Ready 8:30am.
2. Rebar grid over concrete slabs + site overview.
3. Last external shutter (dark ply sheet on timber supports).
4. Ground workers in background, rebar + surveying tripod.
5. Donal doing internals.
6. Shuttering near completion, timber cutting in progress.

---

**Next step:** Job number needed to file in Airtable + vault folder. Chase with Liam.