[IMPORTANT: You are running as a scheduled cron job. DELIVERY: Your final response will be automatically delivered to the user — do NOT use send_message or try to deliver the output yourself. Just produce your report/output as your final response and the system handles the rest. SILENT: If there is genuinely nothing new to report, respond with exactly "[SILENT]" (nothing else) to suppress delivery. Never combine [SILENT] with content — either report your findings normally, or say [SILENT] and nothing more.]

AM look-ahead for Rocky on Hornsby (or whichever job is active in Jobs/Ongoing Jobs/ or Jobs/Upcoming/). Read 00-brief.md, today date 04 Programme/programme-24wk.md row, 06b RFIs/_REGISTER.md (any Cat A still pending), _subbie-schedule.md (anyone booked today), Job-Tracker.md (todays planned activity). Reply with a tight 4-6 line summary on Telegram: today plan, blockers, RFIs to chase, deliveries expected. If nothing notable: just one line saying so.

## Response

**AM Look-Ahead — 01-2275 HPE Field of Play Hornsby — Mon 04 May 2026**

**Today (Wk 2, Mon):** Stair reo begins Day 1 — forming to wrap up, then rebar placement. Pram ramp 1 forming to kick off later in the week with a stair pour targeted before Saturday.

**Blockers:** All 10 Category A RFIs still sitting with Solutions Plus — no responses received. No concrete pump confirmed, no batching plant nominated, no sub-base sign-off, no induction slots booked. Crew physically can't step on site until HammerTech is done. Mobilisation is stalled.

**RFIs to chase:** A3 (pump), A4 (batch plant), A8 (inductions) are the critical path — push Joel Alvey this morning. A1 sub-base and A2 survey handover also needed this week before any pour can proceed.

**Deliveries:** None booked or confirmed. Steel reinforcement (RFI-A9) still pending from Solutions Plus.

**⚠️ CLAIM 1 prep reminder:** Invoice due 25 May — currently zero activity logged in tracker. CC needs to start drafting the claim pack once work kicks off.