[IMPORTANT: You are running as a scheduled cron job. DELIVERY: Your final response will be automatically delivered to the user — do NOT use send_message or try to deliver the output yourself. Just produce your report/output as your final response and the system handles the rest. SILENT: If there is genuinely nothing new to report, respond with exactly "[SILENT]" (nothing else) to suppress delivery. Never combine [SILENT] with content — either report your findings normally, or say [SILENT] and nothing more.]

EOD summary for Rocky on Hornsby (active job). Read todays diary file in 07d Daily Diary/. Read 07a Dockets/ — was todays docket photographed Y/N. Read Job-Tracker.md hours and materials added today. Reply with a tight 5-7 line summary on Telegram: hours logged today, photos saved, docket status (CRITICAL: flag if missing), materials in, tomorrows plan, anything to chase. If docket missing: highlight in red text and remind that no signed docket = no invoice line.

## Response

**EOD Summary — 01-2275 HPE Field of Play Hornsby — 29 April 2026**

**Day type:** Pre-mobilisation (Day 0). No site work. No crew on site.

**Hours logged today:** nil — admin/setup day only.

**Photos saved today:** nil.

**Docket status:** N/A — no work performed on Day 0. No docket required.

**Materials in:** nil.

**Today's actions completed:**
- 10× Cat A RFIs submitted to Solutions Plus via Hasibul — **pending response, chase if no reply before 30 April.**
- B16 working-hours discrepancy — withdrawn, price contract, no dispute.
- Rate card + LFCS folder spec confirmed in place.
- OpsMan/Hermes cron stack live — 4 automated jobs running.

**Tomorrow (30 April — Day 1):**
- Mobilise + HammerTech inductions.
- Confirm sub-base readiness / site access.
- Begin logging crew hours from first on-site day.

**Chase items:**
- ⚠️ **No signed docket on file — irrelevant today (Day 0, no work). Flag reverts to critical from 30 April onwards.** Dayworks rule: no signed docket = no invoice line. Monitor from Day 1.
- RFIs: Awaiting Solutions Plus response before site work begins.