# Cron Job: lfcs-weekly-programme

**Job ID:** f919fa3d1d10
**Run Time:** 2026-05-04 06:01:41
**Schedule:** 0 6 * * 1

## Prompt

[IMPORTANT: You are running as a scheduled cron job. DELIVERY: Your final response will be automatically delivered to the user — do NOT use send_message or try to deliver the output yourself. Just produce your report/output as your final response and the system handles the rest. SILENT: If there is genuinely nothing new to report, respond with exactly "[SILENT]" (nothing else) to suppress delivery. Never combine [SILENT] with content — either report your findings normally, or say [SILENT] and nothing more.]

Weekly programme update for Rocky on Hornsby. Read 04 Programme/programme-24wk.md to know which week we are in. Read Job-Tracker.md float ledger. Read 06b RFIs/_REGISTER.md for open RFIs. Read 08 Variations/_REGISTER.md for raised VOs and pending. Read 05b/_toolbox-talks.md (was a TBT done last week?). Read _inductions-checklist.md (anyone HammerTech expiring within 14 days?). Reply with a tight programme snapshot: week N of 24, float remaining X weeks, work due this week, claim due date if approaching, RFIs to chase, VOs awaiting sign-off, TBT due this week if not yet logged, any inductions expiring.

## Response

**LFCS — Hornsby Weekly Programme Snapshot**
*Cron run: 2026-05-04 Mon 06:00*

---

**Week 1 of 24** | Float: 21 weeks remaining | Target PC: 15 Oct 2026

---

**⚠️ MOBILISATION BLOCKED — Day 1 not yet achieved**

Per 30 Apr diary: crew on site = nil. Cause unconfirmed — EOT trigger flag raised.
No Cat A RFI responses received yet. No crew have turned up.

---

**Work due this week**
- Confirm reason for mobilisation hold with Solutions Plus (Joel Alvey)
- Get Cat A RFI responses in writing — 10 items blocking site access
- HammerTech inductions must be completed before any foot hits the ground

---

**Claim due date**
- **Claim 1 due 25 May** (~$25–35K) — 21 days away. Need mobilisation + progress to support.

---

**RFIs to chase — ALL Cat A items outstanding (no responses recorded)**

| RFI | Blocker |
|-----|---------|
| A1 | S/SE sub-base handover |
| A2 | Survey / setting-out responsibility |
| A3 | Concrete pump — who books, confirmed? |
| A4 | Batching plant nomination |
| A5 | Mix designs (MPa, colour, slump) |
| A6 | Connolly joints on site + storage |
| A7 | Exclusion zones + TC provider operational? |
| A8 | HammerTech induction time slots |
| A9 | Steel mesh/bar delivery + laydown |
| A10 | Blinding layer in place + certified |

**Chase Joel Alvey (1300 653 013 / invoices@solutionsplus.au) today** — without Cat A responses in writing, LFCS is not obligated to mobilise and any delay costs sit with Solutions Plus.

---

**VOs awaiting sign-off**
- VO-001: Curing (Fosroc) — anticipated, pending RFI-B3 response
- VO-002: Sawcuts — anticipated, pending RFI-B4 direction
- VO-003: Avista sealer — anticipated, pending client decision
- **None formally raised yet** — still at anticipated stage

---

**TBT due this week**
- TBT-01 not yet logged. Schedule: every Monday morning.
- Today is Monday — if crew attend site, run Week 1 TBT (Site induction recap + exclusion zones + emergency assembly).
- Log entry required in `05b/_toolbox-talks.md`.

---

**Inductions expiring within 14 days**
- **No expiry dates recorded** in `_inductions-checklist.md` — all fields show TBC.
- Cannot determine risk until Rocky fills in HammerTech done dates and expiry dates.
- **Action: Rocky — confirm HammerTech induction dates for all crew once completed.**

---

**Summary line for Rocky:**
> Mobilisation still held. Chase Joel on all 10 Cat A RFIs today — no written answers = no obligation to turn up. Claim 1 due 25 May needs 3 weeks of actual progress to be credible. TBT to run this morning if anyone's on site. Get HammerTech dates into the register.