🪟 End of Day Digest — 05 Aug ## Queued for decision • **2636 stair pour — anchorage ruling**: Eddie's Z-bars + 'scalpers' form tie, Rocky flagged 'couple of screws into wall' as suspect. Concrete booked 12:00 tomorrow (05/08) — needs engineer/TCE call before concrete lands. Can't wait. • **2636 'pole base' vs 'MSB plinth' naming**: 03/08 wrap filed the day's element as 'pole base/slab'. 31/07 front was 'MSB plinth'. Likely the same pour but the label jumped — one-liner from you confirms before any external mention. • **2631 Hornsby — 4th quiet day in a row**: no roster, no chat activity since 31/07. Worth a touch with Ardi. Carryover pile still open: ramp strip + clean, saw-cut blade + front-face risk, 30/07 pour truck count never banked, stone-basket drawings, 29/07 pipe strike + pit raise + 'other slab', two 27/07 variations unscheduled (extra saw cut + extra Connelly joint). • **2626 Peakhurst — Mack/Jalen paper stale**: written variation + ROL still silent since 04/07. Ray (Arki) email went Sun 05/07 but no reply yet. Ausreo reo requote expired 14/06. TfNSW ROL blackout for week of 19/07 still on your desk (push to Tue 21/07 recommendation). ## Open follow-ups (still waiting on others) • **Jalen (Mack)** — 2626 written variation + ROL determination (was due 10/07). Silent. • **Ray (Arki)** — 2626 night-works delta + walk day + Camellia chase. Email sent Sun evening, no response. • **TCE engineer** — 2636 anchorage sufficiency + 'scalpers' definition. Eddie's wording, design status unconfirmed. • **Concrete supplier (Concrite)** — 2636 stair pour booking for 12:00 tomorrow; office only has Donal's group statement, no supplier confirmation yet. • **Ausreo** — 2626 reo requote (expired 14/06). No fresh quote back. • **Boral (Christine Lane)** — 2626 small-load fee $95/m³ verbal needs locking; specs-not-sighted tie-off still open; lead time unanswered.