  "today": "2026-07-21",
  "counts": {
    "overdue": 34,
    "aged": 4,
    "due7": 25,
    "quiet": 1
  },
  "per_band": [
    2,
    2,
    3,
    1
  ],
  "lines": [
    "PM Tue 21/7 20:13 \u2014 2 of 34 overdue, 2 of 4 aged-waiting, 3 of 25 due<=7d, 1 quiet",
    "\ud83d\udd34 OVERDUE:",
    "2650 Macarthur: verify outcome \u2014 due 1/7 passed, go/no-go undecided; ask Garr... \u2014 due Sat 4/7",
    "2649 seats DECIDED back IN (fab supplies units, LFCS installs) - send 2 held ... \u2014 due Sat 4/7",
    "(+32 more)",
    "\ud83d\udd34 AGED WAITING:",
    "2633 Tamplin: chase award status \u2014 submitted 22/5, 6 weeks silent \u2014 waiting 42d",
    "2646 MOWA: chase Isaac \u2014 pricing questions email 3 weeks unanswered \u2014 waiting 26d",
    "(+2 more)",
    "\ud83d\udfe1 DUE \u22647d:",
    "2626 DAYWORKS THREAD \u2014 RFI 36 (TfNSW response 13/02) instructs this pit under... \u2014 due Tue 21/7",
    "2626 SEND the Ray->Jalen pipe/invert draft (sitting in Gmail DRAFTS) \u2014 attach... \u2014 due Tue 21/7",
    "2631 VAR-005 beam: SCREENSHOT the pre-pour paper onto the job file \u2014 engineer... \u2014 due Wed 22/7",
    "(+22 more)",
    "\u26aa QUIET: 2636 no diary filed"
  ],
  "overdue_items": [
    "2650 Macarthur: verify outcome \u2014 due 1/7 passed, go/no-go undecided; ask Garr... \u2014 due Sat 4/7",
    "2649 seats DECIDED back IN (fab supplies units, LFCS installs) - send 2 held ... \u2014 due Sat 4/7",
    "2649 chase Draffin (silent since 30/06) + nudge Street Furniture Aust - timbe... \u2014 due Sat 4/7",
    "2649 Shaun (Delta) confirms - slotted K&G rate ($70 vs $26), profiles TCI-020... \u2014 due Sun 5/7",
    "2649 Liam go/no-go \u2192 final pack (LoO + Part F BoQ, both kerb options) \u2192 Rocky... \u2014 due Sun 5/7",
    "2636 paste site-brief.md into '2636 Liverpool \u2014 Site Diary' Telegram group (r... \u2014 due Mon 6/7",
    "2652 site measure per unit Mon 6/7 before ordering ply/concrete \u2014 due Mon 6/7",
    "2636 confirm job name = Light Horse Park Redevelopment Stage 1 \u2192 rename folde... \u2014 due Tue 7/7",
    "2636 approve Airtable Jobs note fix Donald \u2192 Donal Murphy (gated) \u2014 due Tue 7/7",
    "2636 fill site-brief who's-who gaps \u2014 Daniel's (TCE) surname + mobile, TCE si... \u2014 due Tue 7/7",
    "2654 Civic Link: Assad takeoff due Mon 7/7 \u2014 reconcile vs the 5 known Sol+ er... \u2014 due Tue 7/7",
    "2654 send 2-question RFI to Christian (IFC status + program) \u2014 draft ready \u2014 due Tue 7/7",
    "2649 verify QTE#0068973 (Drive 07/07) covers seat subframes \u2192 firm PROV seat/... \u2014 due Tue 7/7",
    "2648 reply to Assad Mon - retrace reconcile deltas (RW1 conc/fw swapped again... \u2014 due Tue 7/7",
    "2636 verify INV#959 payment status ($30,577.80 inc GST, was overdue 30/04) wi... \u2014 due Wed 8/7",
    "2636 confirm 11-May dayworks items (3hr hold, 300mm clearance shortfall, extr... \u2014 due Wed 8/7",
    "2645 ZEB: chase Paul Clipsham - AFC tender pack + verify round still open (AS... \u2014 due Wed 8/7",
    "2651 confirm PL insurance min + relief-valve supply + screw-pier scope with C... \u2014 due Wed 8/7",
    "2626 pre-start runway \u2014 /mob gates + SWMS (folder 05) + Ausreo reo requote (e... \u2014 due Wed 8/7",
    "2626 TfNSW ROL BLACKOUT check \u2014 winter school-holiday restriction schedule fo... \u2014 due Wed 8/7",
    "2626 temp works design deliverable - pin ownership at pre-start walk (methodo... \u2014 due Wed 8/7",
    "2631 build ITP + SWMS before pour-ready hold Fri 10/7 \u2014 due Thu 9/7",
    "2631 review 'Concrete Package - Pavements added scope.pdf' + new IFC (Drive 0... \u2014 due Thu 9/7",
    "2630 works agreement payment clause \u2014 45d EOM is VOID vs SOPA s11(1B) (20 bus... \u2014 due Sat 11/7",
    "2630 do NOT sign with LD cl 4.2 blank \u2014 blank/nil = UNCAPPED at-large delay d... \u2014 due Sat 11/7",
    "2630 FFP cl 11.5-11.9 \u2014 push to 'construct per design with due skill and care... \u2014 due Sat 11/7",
    "2630 add works-agreement qualifications \u2014 dependency schedule (setout S130-S1... \u2014 due Sat 11/7",
    "2631 clean up diary rows \u2014 merge duplicate 16/06, move 9/7 block out of 8/7 r... \u2014 due Mon 13/7",
    "2626 when Mack paper (PO/subcontract/reissued MWA) lands \u2014 diff it against RE... \u2014 due Tue 14/7",
    "2626 if 19/07 slips \u2014 same-day off-hire/redeploy (mitigation duty verified; s... \u2014 due Tue 14/7",
    "2626 Boral residuals before first pour \u2014 tie price to R53 mix codes 137941/13... \u2014 due Tue 14/7",
    "2631 check the 16/07 slab for rain damage \u2014 photos, and it's S+ exposure not ... \u2014 due Fri 17/7",
    "2651 Carlo replied to at last (SENT 17/07) - waiting on his answer re groundw... \u2014 due Fri 17/7",
    "2648 BIN dead $29,803 draft -> send place-only $17,575.62 to Christian \u2014 due Fri 17/7"
  ],
  "aged_items": [
    "2633 Tamplin: chase award status \u2014 submitted 22/5, 6 weeks silent \u2014 waiting 42d",
    "2646 MOWA: chase Isaac \u2014 pricing questions email 3 weeks unanswered \u2014 waiting 26d",
    "2635 Hammond: chase TCE on REV2 \u2014 18 days silent \u2014 waiting 12d",
    "2649 Hass mapping our Rev A rates onto NSP/Council BoQ - REVIEW GATE: Rocky c... \u2014 waiting 10d"
  ],
  "due7_items": [
    "2626 DAYWORKS THREAD \u2014 RFI 36 (TfNSW response 13/02) instructs this pit under... \u2014 due Tue 21/7",
    "2626 SEND the Ray->Jalen pipe/invert draft (sitting in Gmail DRAFTS) \u2014 attach... \u2014 due Tue 21/7",
    "2631 VAR-005 beam: SCREENSHOT the pre-pour paper onto the job file \u2014 engineer... \u2014 due Wed 22/7",
    "2631 VAR-005 beam: capture strip+finish person-hrs at pour (22/07) over 35.5m... \u2014 due Wed 22/7",
    "2651 Camellia: LIAM DECISION - do we supply concrete+pump or labour-only? (ha... \u2014 due Wed 22/7",
    "2651 Camellia: FIRE Acrow single-sided form RFQ (biggest price unknown) \u2014 due Wed 22/7",
    "2626 get WRITTEN acceptance + ROL determination out of Jalen \u2014 nothing is on ... \u2014 due Wed 22/7",
    "2626 whole-day one-lane closure is now the PRICE BASIS \u2014 get it in writing fr... \u2014 due Wed 22/7",
    "2626 RFI 36 CONTRACTOR ACCEPTANCE STILL UNSIGNED \u2014 verified 17/07 (p5 'Not si... \u2014 due Wed 22/7",
    "2626 RAY OWES THE ROCK ANSWER \u2014 geotech (2020, intersection boreholes) shows ... \u2014 due Wed 22/7",
    "2626 SL82 MESH QUOTE \u2014 line 1.6 WENT OUT UNSOURCED. Rev E carries reo supply ... \u2014 due Wed 22/7",
    "2631 CVR pkg 007 reconcile - VAR-005 beam cost basis disagrees across files (... \u2014 due Thu 23/7",
    "2651 Camellia: trace 260695 in zzTakeoff -> CSV -> eng prices BoQ v2 \u2014 due Thu 23/7",
    "2651 Camellia: SEND priced quote + written exclusions to Carlo (promise: Thu ... \u2014 due Thu 23/7",
    "2626 REISSUED MWA \u2014 DO NOT SIGN UNTIL IT READS $57,300 AND NAMES REV E. Rev E... \u2014 due Thu 23/7",
    "2626 ROCK QUALIFICATION INTO THE QUOTE DOCS once Ray answers \u2014 Rev P2 Section... \u2014 due Thu 23/7",
    "2626 CONCRETE ROUTE decision \u2014 Hy-Tec approved R53 mix (Jalen offered, no hol... \u2014 due Thu 23/7",
    "2626 MOB GATE: PL COC $20M + Workers Comp COC \u2014 pull both certificates from o... \u2014 due Fri 24/7",
    "2626 MOB GATE: SWMS \u2014 revise SWMS 08 (folder 11) from the old method to the d... \u2014 due Fri 24/7",
    "2626 MWA REISSUE \u2014 ASK FOR THE WEATHER FIX WHILE IT IS OPEN. As drafted, incl... \u2014 due Fri 24/7",
    "2626 REO TRADE \u2014 HOLD IT, DO NOT VOLUNTEER IT. If Mack grinds line 1.6: offer... \u2014 due Fri 24/7",
    "2652 Rev F SENT to Hayden 17/07 - LETTER ONLY, no BoQ. Waiting on Ford \u2014 due Fri 24/7",
    "2626 MOB GATE: Inductions (TfNSW/Mack) + First-aider + nearest hospital on em... \u2014 due Sat 25/7",
    "2626 NO BUILDUP BEHIND $57,300. The latest buildup is v11 (15/06, 9 shifts @ ... \u2014 due Mon 27/7",
    "2630 HARD GATE \u2014 no mobilisation cost before executed agreement or binding wr... \u2014 due Tue 28/7"
  ],
  "quiet_items": [
    "2636 no diary filed"
  ]
}